Kedar Residency, Mamurdi
Lapsed
by Subhagya Promoters & Builders Pvt Ltd. Mamurdi, Pune 412101. View on Google Maps
- Launched
- 4 years promised
- Possession date (MahaRERA)
- 10 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 97 of 12876% booked
Project facts
| 1 BHK | 17 |
|---|---|
| 2 BHK | 91 |
| Other units (shops, offices or not given by type) | 20 |
| Total units | 128 |
| Buildings | 1 |
| Land | 0.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 33 → 97
Compared with 6 similar projects in PIN 412101
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs | 4 yrs |
| Possession date extended | No | 2 of 6 |
| Possession date passed | Yes, due December 2025 | 5 ready to move; 1 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 76% | 98% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ace Abode Wing A | December 2021 | December 2025 | 100% | All 107 units booked |
| Maheshwaram Majestic | December 2021 | June 2026 | 100% | 63 of 126 booked (50%) |
| Ace Abode Wing B | February 2022 | December 2025 | 100% | 79 of 81 booked (98%) |
| Star Vista | October 2021 | April 2025 | 100% | 130 of 150 booked (87%) |
| Om Mangalam Yash | March 2022 | December 2026 | 100% | 221 of 229 booked (97%) |
| Ace Abode Phase 2B | May 2022 | June 2027 | 100% | All 78 units booked |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 97 | |
| 100% | 100% | 0% | 33 | |
| 100% | 92% | 0% | 33 | |
| 100% | 85% | 0% | 33 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Kedar Residency (MahaRERA P52100032109) is a residential project by Subhagya Promoters & Builders Pvt Ltd in Mamurdi, Pune 412101. It was launched in December 2021. It has 128 units in 1 building: 108 homes (1 & 2 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.
97 of its 128 units are booked (76%). Since the December 2025 update, 64 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.