Skip to main content
← Back

Majestique Marbella Phase V, Kharadi

by Majestique Empire LLP. Kharadi, Pune 411014. View on Google Maps

Launched
4 years 11 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possessionAverage across 2 buildings
Units booked
107 of 15768% booked

Project facts

1 BHK3
2 BHK103
3 BHK51
Total units157
Buildings2
Land1 acre
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 3 similar projects in PIN 411014

Projects with 70–350 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411014
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 11 mths4 yrs 11 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)December 2026August 2027
Concrete structure (RCC) complete100%100%
Share of units booked68%93%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 9 months of the promised 4 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 8%Jun 2024: Concrete structure (RCC) 8%Dec 2024: Concrete structure (RCC) 8%Jun 2025: Concrete structure (RCC) 8%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%107
100%8%0%107
100%8%0%99

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Majestique Marbella Phase V (MahaRERA P52100032450) is a residential project by Majestique Empire LLP in Kharadi, Pune 411014. It was launched in January 2022. It has 157 units in 2 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.

107 of its 157 units are booked (68%).

Majestique's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA74
Completed without extending the possession date35
Completed after an extension, or lapsed9
Under construction30
Possession date extended by the builder1
Typical time from launch to 100% structure3 years 8 months
Complaints on MahaRERA, all Majestique projects30 (11 of 74 projects)

See all Majestique projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100032450.Check it on MahaRERA (P52100032450)All projects in Kharadi, Vadgaon Sheri, Viman Nagar