Pristine Allure Part 1, Kharadi
by Mahalaxmi Shelters. Kharadi, Pune 411014. View on Google Maps
- Launched
- 5 years 7 months promised
- Possession date (MahaRERA)
- 1 year 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 4 buildings
- Units booked
- 290 of 31193% booked
- Price per sq ft (incl. balconies and terrace)
- ₹10,3002025 · 12 salesup 2% on 202480% of the 2025 sales we found were at this rate or lessSee what buyers paid
Project facts
| 1 BHK | 5 |
|---|---|
| 2 BHK | 182 |
| 3 BHK | 124 |
| Total units | 311 |
| Buildings | 4 |
| Land | 2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 2 |
Since Dec 2025: complaints 0 → 2
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 760 – 960 sq ft | ₹74 – 91 lakh |
Based on flats sold in 2025.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2024 | ₹10,100 per sq ft | 30 sales |
|---|---|---|
| 2025up 2% on 2024 | ₹10,300 per sq ft | 12 sales |
Compared with 5 similar projects in PIN 411014
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 7 mths | 4 yrs 11 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | December 2027 | December 2026 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 93% | 68% |
| Complaints on MahaRERA (filed by or against the builder) | 2 | 1 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Riverdale Grand | April 2022 | September 2028 | 56% | 321 of 615 booked (52%) |
| ZEN Elite | February 2022 | December 2026 | 100% | 391 of 446 booked (88%) |
| The Collection Premium | January 2022 | December 2026 | 100% | 288 of 322 booked (89%) |
| Majestique Marbella Phase V | January 2022 | December 2026 | 100% | 107 of 157 booked (68%) |
| Unique Youtopia Phase III | October 2022 | September 2026 | 100% | 262 of 474 booked (55%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 290 | |
| 100% | 68% | 0% | 239 | |
| 100% | 68% | 0% | 209 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Pristine Allure Part 1 (MahaRERA P52100045237) is a residential project by Mahalaxmi Shelters in Kharadi, Pune 411014. It was launched in May 2022. It has 311 units in 4 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) complete, final finishes not started. MahaRERA records do not show it as ready to move in.
290 of its 311 units are booked (93%). 80% of the 2025 sales we found here were at ₹10,300 per sq ft or less (up 2% on 2024), counting balconies and terrace in the size, based on 12 registered sales. Most buyers paid ₹74–91 lakh for flats of 760–960 sq ft.
Pristine's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 25 |
|---|---|
| Completed without extending the possession date | 13 |
| Completed after an extension, or lapsed | 1 |
| Under construction | 11 |
| Possession date extended by the builder | 1 |
| Typical time from launch to 100% structure | 2 years 7 months |
| Complaints on MahaRERA, all Pristine projects | 18 (6 of 25 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.