Skip to main content
← Back

Abhimaan Homes Phase 3, Shirgaon

by Rising Propcon LLP. Shirgaon, Pune 410506. View on Google Maps

Launched
4 years 11 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possessionAverage across 5 buildings
Units booked
422 of 52181% booked

Project facts

1 BHK330
2 BHK191
Total units521
Buildings5
Land2.5 acres
Complaints on MahaRERA (filed by or against the builder)2

Since Dec 2025: booked 382 → 422

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 9 months of the promised 4 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 77%Jun 2024: Concrete structure (RCC) 90%Dec 2024: Concrete structure (RCC) 97%Jun 2025: Concrete structure (RCC) 97%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 4%Dec 2024: Final finishes 27%Jun 2025: Final finishes 27%Dec 2025: Final finishes 85%Jul 2026: Final finishes 85%Excavation 100%Concrete structure (RCC) 100%Final finishes 85%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%85%422
100%100%85%382
100%97%27%229
100%90%4%107
100%77%0%107

"—" means MahaRERA shows no figure for that update.

About this project

Abhimaan Homes Phase 3 (MahaRERA P52100032485) is a residential project by Rising Propcon LLP in Shirgaon, Pune 410506. It was launched in January 2022. It has 521 units in 5 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 5 buildings: excavation complete, structure (RCC) complete, final finishes 85% complete. MahaRERA records do not show it as ready to move in.

422 of its 521 units are booked (81%). Since the December 2025 update, 40 more units have been booked.

Kohinoor's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA48
Completed without extending the possession date13
Completed after an extension, or lapsed10
Under construction25
Possession date extended by the builder8
Typical time from launch to 100% structure3 years 3 months
Complaints on MahaRERA, all Kohinoor projects52 (19 of 48 projects)

See all Kohinoor projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100032485.Check it on MahaRERA (P52100032485)All projects in Talegaon Dabhade, Darumbare