Kohinoor projects in Pune
Every MahaRERA project by Kohinoor in the 59 areas FlatNama covers, registered 2017–2026.
- Registered
- 482017–2026
- Under construction
- 25
- Completed
- 1713 without extending
- Complaints
- 52across 19 of 48
Track record
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 48 |
|---|---|
| Completed without extending the possession date | 13 |
| Completed after an extension, or lapsed | 10 |
| Under construction | 25 |
| Possession date extended by the builder | 8 |
| Typical time from launch to 100% structure | 3 years 3 months |
| Complaints on MahaRERA, all Kohinoor projects | 52 (19 of 48 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Maan (6) · Tathawade (4) · Wagholi (4) · Punawale (3) · Dhanori (2) · Bhugaon (2) · Wakad (2) · Pimple Saudagar (1) · Hadapsar (1) · Bhosari (1)
Under construction (25)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Abhimaan Homes Phase 3 | Shirgaon | Nearing possession | December 2026 | 422 of 521 booked (81%) |
| Courtyard One C Bldg | Wakad | Finishing stage | December 2026 | 242 of 257 booked (94%) |
| Kohinoor Avantara | Tathawade | Early stage | March 2032 | |
| Kohinoor Central Park - Phase 1 | Maan | Mid-construction | December 2028 | 767 of 1,095 booked (70%) |
| Kohinoor Central Park - Phase II | Maan | Early stage | October 2029 | 372 of 553 booked (67%) |
| Kohinoor Famville | Maan | Nearing possession | December 2028 | 633 of 736 booked (86%) |
| Kohinoor Iris Park Phase II | Hadapsar | Nearing possession | December 2026 | 24 of 53 booked (45%) |
| Kohinoor Kaleido | Wagholi | Nearing possession | December 2027 | 823 of 832 booked (99%) |
| Kohinoor Kaleido-Phase-II | Wagholi | Mid-construction | October 2029 | 147 of 505 booked (29%) |
| Kohinoor Regalia Towers | Wakad | Early stage | June 2030 | 66 of 148 booked (45%) |
| Kohinoor Riverdale | Wagholi | Mid-construction | December 2028 | 466 of 648 booked (72%) |
| Kohinoor Riverdale - Phase II | Wagholi | Mid-construction | December 2028 | 92 of 428 booked (21%) |
| Kohinoor Royale Towers | Hinjewadi | Early stage | December 2030 | |
| Kohinoor Satori Mahalunge | Maan | Early stage | December 2029 | 199 of 448 booked (44%) |
| Kohinoor Uptown Avenue | Punawale | Early stage | December 2029 | 615 of 950 booked (65%) |
| Kohinoor Viva Pixel- Phase II | Dhanori | Mid-construction | June 2028 | 403 of 624 booked (65%) |
| Kohinoor Westview Reserve | Punawale | Mid-construction | December 2028 | 718 of 794 booked (90%) |
| Kohinoor Westview Reserve-II | Punawale | Nearing possession | December 2028 | 440 of 484 booked (91%) |
| Kohinoor Woodshire | Bhugaon | Early stage | December 2029 | 121 of 493 booked (25%) |
| Kohinoor Woodshire Phase 2 | Bhugaon | Early stage | December 2030 | |
| S3 Lifestyle | Pimple Saudagar | Nearing possession | January 2022 | 55 of 63 booked (87%) |
| Sportsville | Maan | Mid-construction | December 2026 | 431 of 459 booked (94%) |
| Sportsville Phase 1 | Maan | Nearing possession | December 2027 | 54 of 70 booked (77%) |
| Vision Selekt | Bhosari | Early stage | March 2028 | |
| ZEN Elite | Kharadi | Finishing stage | December 2026 | 391 of 446 booked (88%) |
Completed (17)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Courtyard One phase 2 | ||||
| Kohinoor Begonia Phase III | ||||
| Kohinoor Blisspark | ||||
| Kohinoor Coral | Ready to move | December 2024 | 277 of 433 booked (64%) | |
| Kohinoor Grandeur | Kiwale | Ready to move | March 2024 | All 62 units booked |
| Kohinoor Iris Park | ||||
| Kohinoor Jeeva | ||||
| Kohinoor Jeeva C Building | ||||
| Kohinoor Majesty Wing A | ||||
| Kohinoor Sapphire | Tathawade | Ready to move | December 2024 | 489 of 498 booked (98%) |
| Kohinoor Sapphire II | Tathawade | Ready to move | September 2024 | 418 of 423 booked (99%) |
| Kohinoor Shangrila Phase 2 | Ready to move | December 2025 | All 260 units booked | |
| Kohinoor Shangrila Phase I | Ready to move | December 2018 | ||
| Tinsel County Phase I | ||||
| Tinsel County Phase II | ||||
| Tinsel Town Phase I | ||||
| Tinsel Town Phase II |
Lapsed (6)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Kohinoor Emerald 1 | Sus | Finishing stage | September 2024 | 52 of 60 booked (87%) |
| Kohinoor Jeeva B Wing | ||||
| Kohinoor Sapphire III | Tathawade | Nearing possession | February 2026 | 462 of 480 booked (96%) |
| Kohinoor Viva Pixel- Phase I | Dhanori | Finishing stage | June 2026 | 48 of 96 booked (50%) |
| Olive Bliss | ||||
| Presidentia | Ghorpadi | Finishing stage | December 2025 | 147 of 200 booked (74%) |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.