- Launched
- Jan 20224 yrs 5 mths originally promised
- Possession (MahaRERA)
- Apr 2028Extended by 1 yr 10 mths
- Concrete structure
- 100%Average of 2 towers
- Booked
- 72 of 20735%
- Price per sq ft
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 51
- 3 BHK
- 156
- Total units
- 207
- Buildings
- 2
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
From the architect's Form 1 filed with MahaRERA, latest filing Apr 2025. The last 4 updates per tower.
How construction has progressed
Each point is a progress report the builder's architect filed with MahaRERA (Form 1). A line that stays flat means no new progress was reported between two dates.
Last 4 updates, tower by tower
| Update | Structure | Finishes |
|---|---|---|
| Apr 2025 | 100% | 90% |
| Jan 2025 | 100% | 90% |
| Jul 2024 | 100% | 85% |
| Apr 2024 | 100% | 87% |
| Update | Structure | Finishes |
|---|---|---|
| Apr 2025 | 100% | 90% |
| Jan 2025 | 100% | 90% |
| Jul 2024 | 100% | 85% |
| Apr 2024 | 100% | 80% |
Excavation is 100% in every tower.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 72 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Construction cost spent
From the engineer's Form 2 filed with MahaRERA.
₹43.9 crore spent · latest estimate ₹50.9 crore · May 2025
Spent at each update
| Update | Spent |
|---|---|
| May 2025 | ₹43.9 crore |
| Jan 2025 | ₹43.7 crore |
| Jul 2024 | ₹39.8 crore |
| Apr 2024 | ₹39.8 crore |
Compared with 6 similar projects in PIN 412105
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 5 mths | 3 yrs 6 mths |
| Possession date extended | By 1 yr 10 mths | 6 of 6 |
| Possession date (MahaRERA) | Apr 2028 | Jun 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 35% | 86% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects, latest price per sq ft
- Aksha Ambar, Dudulgaon
- Omkar Residency, Moshi
- Amora Tower, Charholi Budruk₹6,500 · 2026
- Destination 24 Avenue, Charholi Budruk₹6,000 · 2026
- Kamalraj Dattavihar E and H, Moshi
- SnehaSparsha Residency, Alandi
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Aksha Ambar | January 2022 | Jun 2025 – Dec 2027 | 100% | 250 units booked out of total 299 units |
| Omkar Residency | February 2022 | September 2026 | 100% | 155 units booked out of total 210 units |
| Amora Tower | December 2021 | December 2026 | 100% | 102 units booked out of total 116 units |
| Destination 24 Avenue | February 2022 | Mar 2026 – Mar 2027 | 100% | 226 units booked out of total 357 units |
| Kamalraj Dattavihar E and H | November 2021 | December 2025 | 100% | 199 units booked out of total 224 units |
| SnehaSparsha Residency | November 2021 | December 2026 | 100% | 138 units booked out of total 155 units |
About this project
The Address PHASE-4 by SOL Developers is a 207-unit project in Moshi, Pune 412105, launched in January 2022 with possession due in April 2028. 72 units booked out of total 207 units. The concrete structure (RCC) is complete.
Read full summary
The Address PHASE-4 is a project by SOL Developers in Moshi, Pune 412105, registered with MahaRERA as P52100032678. It was launched in January 2022. It has 207 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2028, extended by 1 year 10 months from the original June 2026. Construction, averaged across its 2 towers: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
72 units booked out of total 207 units (35%).