Skip to main content
← Back

Essenciya, Wanawadi

Lapsed

by M/S. Flynirvanna Builder LLP. Wanawadi, Pune 411040. View on Google Maps

Launched
2 years 1 month originally promised
Possession date (MahaRERA)
1 year 4 months ago. No further extension recordedExtended by 1 year 3 months (originally March 2024). What "Lapsed" means
Concrete structure (RCC)
100%Nearing possession
Units booked
1 of 215% booked

Project facts

2 BHK7
3 BHK14
Total units21
Buildings1
Land0.1 acres
Landowner share12
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: final finishes 40% → 70%

Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 2 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 25%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 40%Dec 2024: Final finishes 40%Jun 2025: Final finishes 40%Dec 2025: Final finishes 40%Jul 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 100%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%70%1
100%100%40%—
100%25%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Essenciya (MahaRERA P52100032828) is a residential project by M/S. Flynirvanna Builder LLP in Wanawadi, Pune 411040. It was launched in February 2022. It has 21 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 1 year 3 months from the original March 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete. MahaRERA records do not show it as ready to move in.

1 of its 21 units is booked (5%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100032828.Check it on MahaRERA (P52100032828)All projects in Wanawadi, Fatimanagar