Kesar Treetown Phase 3, Moshi
by Kesar Vighnaharta Group. Moshi, Pune 412105. View on Google Maps
- Launched
- 3 years 7 months originally promised
- Possession date (MahaRERA)
- 2 months awayExtended by 1 year (originally December 2025). Why possession dates change
- Concrete structure (RCC)
- 67%Mid-constructionAverage across 2 buildings
- Units booked
- 259 of 29189% booked
Project facts
| 2 BHK | 164 |
|---|---|
| 3 BHK | 112 |
| Other units (shops, offices or not given by type) | 15 |
| Total units | 291 |
| Buildings | 2 |
| Land | 2.3 acres |
| Landowner share | 19 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 0% → 67% · final finishes 0% → 67% · possession date December 2025 → December 2026
Compared with 6 similar projects in PIN 412105
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 7 mths | 4 yrs 1 mth |
| Possession date extended | By 1 year | 1 of 6 |
| Possession date (MahaRERA) | December 2026 | May 2028 |
| Concrete structure (RCC) complete | 67% | 100% |
| Share of units booked | 89% | 84% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Wellington-l-m | June 2022 | September 2026 | 100% | 258 of 264 booked (98%) |
| Royal Square | June 2022 | May 2028 | 91% | 146 of 216 booked (68%) |
| BLOOM RESIDENCY - A, B and Commercial Wing | April 2022 | December 2025 | 100% | 79 of 218 booked (36%) |
| Shivteerth Legacy Wing B and C | April 2022 | March 2026 | 100% | 121 of 155 booked (78%) |
| Spring Valley Phase III | February 2022 | December 2029 | 97% | 268 of 294 booked (91%) |
| Soho | August 2022 | April 2026 | 100% | All 363 units booked |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 67% | 67% | 67% | 259 | |
| 0% | 0% | 0% | 259 | |
| 0% | 0% | 0% | 174 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Kesar Treetown Phase 3 (MahaRERA P52100045320) is a residential project by Kesar Vighnaharta Group in Moshi, Pune 412105. It was launched in May 2022. It has 291 units in 2 buildings: 276 homes (2 & 3 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction, averaged across its 2 buildings: excavation 67% complete, structure (RCC) 67% complete, final finishes 67% complete. MahaRERA records do not show it as ready to move in.
259 of its 291 units are booked (89%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 67% and the possession date has moved from December 2025 to December 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.