Skip to main content
← Back

Balaji Siddhi, Ambegaon Budruk

by Shri Balaji Siddhi Developers. Ambegaon Budruk, Pune 411046. View on Google Maps

Launched
4 years 1 month originally promised
Possession date (MahaRERA)
1 year awayExtended by 1 year 7 months (originally March 2026). Why possession dates change
Concrete structure (RCC)
100%Nearing possessionAverage across 2 buildings
Units booked
65 of 15243% booked

Project facts

1 BHK102
2 BHK46
3 BHK4
Total units152
Buildings2
Land0.7 acres
Landowner share64
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 35 → 65 · structure 30% → 100% · final finishes 0% → 45% · possession date March 2026 → October 2027

Share on WhatsApp

Compared with 3 similar projects in PIN 411046

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 411046
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 1 mth5 yrs 10 mths
Possession date extendedBy 1 year 7 months1 of 3
Possession date (MahaRERA)October 2027December 2027
Concrete structure (RCC) complete100%70%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 30%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 45%Excavation 100%Concrete structure (RCC) 100%Final finishes 45%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%45%65
100%30%0%35
100%0%0%2

"—" means MahaRERA shows no figure for that update.

About this project

Balaji Siddhi (MahaRERA P52100033044) is a residential project by Shri Balaji Siddhi Developers in Ambegaon Budruk, Pune 411046. It was launched in February 2022. It has 152 units in 2 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2027, extended by 1 year 7 months from the original March 2026. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 45% complete. MahaRERA records do not show it as ready to move in.

65 of its 152 units are booked (43%). Since the December 2025 update, 30 more units have been booked, the reported concrete structure (RCC) has gone from 30% to 100% and the possession date has moved from March 2026 to October 2027.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100033044.Check it on MahaRERA (P52100033044)All projects in Ambegaon, Katraj