Padmavati Hills, Bavdhan Budruk
by Suyog City Developers. Bavdhan Budruk, Pune 411021. View on Google Maps
- Launched
- First of 2 phases
- Possession dates (MahaRERA)
- Dec 2025 – Mar 2027varies by phaseNo phase has an extended possession date
- Concrete structure (RCC)
- 77%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
- Units booked
- 35 of 5267% booked
Facts
Project facts
| 3 BHK | 41 |
|---|---|
| 4 BHK | 11 |
| Total units | 52 |
| Buildings | 2 |
| Land | 0.6 acres |
| Phases | 2 |
Since Dec 2025: booked 33 → 35
Shortlist 2 or more to compare side by side.
Phases
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Padmavati Hills K Wing Nearing possession Lapsed | P52100033108 | 12 | 100% | 100% | |
| Padmavati Hills A Wing Mid-construction | P52100052667 | 40 | 70% | 58% |
Show updates by phase
Padmavati Hills K Wing (P52100033108)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 12 | |
| 100% | 100% | 0% | 9 |
"—" means MahaRERA shows no figure for that update.
Padmavati Hills A Wing (P52100052667)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 23 | |
| 100% | 15% | 0% | 21 | |
| 100% | 0% | 0% | 27 | |
| 100% | 0% | 0% | 10 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 5 similar projects in PIN 411021
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 8 mths | 4 yrs 11 mths |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | Dec 2025 – Mar 2027 | April 2027 |
| Concrete structure (RCC) | 77% | 100% |
| Units booked | 67% | 73% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rising Hills | February 2022 | August 2026 | 100% | 13 of 40 booked (33%) |
| Green Valley | March 2022 | June 2028 | 100% | 63 of 70 booked (90%) |
| Wishful 60 Exotica | May 2022 | April 2027 | 80% | 19 of 45 booked (42%) |
| Kumar Sanctum - A2 And B2 | May 2022 | December 2026 | 100% | 52 of 66 booked (79%) |
| Freshia Identity | June 2022 | June 2027 | 0% | Bookings not reported |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
Padmavati Hills is a project by Suyog City Developers in Bavdhan Budruk, Pune 411021, registered with MahaRERA as 2 phases (P52100033108, P52100052667). The first phase was launched in February 2022. Together the phases have 52 units in 2 buildings, with 3 & 4 BHK homes as registered with MahaRERA. On MahaRERA, 1 is lapsed and 1 is active.
The phases' registered possession dates run from December 2025 to March 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 77% complete and final finishes 0% complete. 1 of the 2 phases have their structure complete.
35 of the 52 units reported for sale are booked (67%).