Skip to main content
← Back

Spring Valley Phase III, Charholi

by Shubh Ganesh Properties. Charholi, Pune 412105. View on Google Maps

Launched
7 years 10 months promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
97%Mid-constructionAverage across 3 buildings
Units booked
268 of 29491% booked

Project facts

2 BHK294
Total units294
Buildings3
Land2.5 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 213 → 268 · structure 92% → 97%

Share on WhatsApp

Compared with 6 similar projects in PIN 412105

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)7 yrs 10 mths3 yrs 10 mths
Possession date extendedNo5 of 6
Possession date (MahaRERA)December 2029December 2026
Concrete structure (RCC) complete97%100%
Share of units booked91%78%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 8 months of the promised 7 years 10 months have passed
Concrete structure (RCC) 97% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 97%Jun 2024: Excavation 97%Dec 2024: Excavation 97%Jun 2025: Excavation 97%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 47%Jun 2024: Concrete structure (RCC) 47%Dec 2024: Concrete structure (RCC) 67%Jun 2025: Concrete structure (RCC) 67%Dec 2025: Concrete structure (RCC) 92%Jul 2026: Concrete structure (RCC) 97%Dec 2023: Final finishes 33%Jun 2024: Final finishes 33%Dec 2024: Final finishes 33%Jun 2025: Final finishes 33%Dec 2025: Final finishes 72%Jul 2026: Final finishes 72%Excavation 100%Concrete structure (RCC) 97%Final finishes 72%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%97%72%268
100%92%72%213
97%67%33%112
97%47%33%112
97%47%33%71

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Spring Valley Phase III (MahaRERA P52100033571) is a residential project by Shubh Ganesh Properties in Charholi, Pune 412105. It was launched in February 2022. It has 294 units in 3 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 97% complete, final finishes 72% complete. MahaRERA records do not show it as ready to move in.

268 of its 294 units are booked (91%). Since the December 2025 update, 55 more units have been booked and the reported concrete structure (RCC) has gone from 92% to 97%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100033571.Check it on MahaRERA (P52100033571)All projects in Charholi, Moshi