Gulmohar 24, Chovisawadi
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Royal Gulmohar Reality. Chovisawadi, Pune 412105. View on Google Maps
- Launched
- 3 years 9 months originally promised
- Possession date (MahaRERA)
- 1 month agoExtended by 9 months (originally December 2025). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 72 of 8387% booked
Project facts
| 1 BHK | 29 |
|---|---|
| 2 BHK | 54 |
| Total units | 83 |
| Buildings | 1 |
| Land | 0.4 acres |
| Landowner share | 11 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: possession date December 2025 → September 2026
Compared with 6 similar projects in PIN 412105
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 9 mths | 3 yrs 10 mths |
| Possession date extended | By 9 months | 3 of 6 |
| Possession date (MahaRERA) | September 2026 | June 2027 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 87% | 60% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kalpavruksha-phase-I- A and B | March 2022 | December 2027 | 35% | Bookings not reported |
| Suvarna Nagari PH-2 | March 2022 | December 2026 | 100% | 59 of 110 booked (54%) |
| Flower City | February 2022 | December 2025 | 100% | 58 of 77 booked (75%) |
| L-square Prime | April 2022 | December 2026 | 100% | 14 of 55 booked (25%) |
| Anthesis | February 2022 | December 2028 | 32% | 49 of 82 booked (60%) |
| Destination 24 Avenue C Building | February 2022 | December 2025 | 100% | 136 of 169 booked (80%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 72 | |
| 100% | 100% | 0% | — | |
| 100% | 10% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Gulmohar 24 (MahaRERA P52100033662) is a residential project by Royal Gulmohar Reality in Chovisawadi, Pune 412105. It was launched in March 2022. It has 83 units in 1 building, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2026, extended by 9 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
72 of its 83 units are booked (87%). Since the December 2025 update, the possession date has moved from December 2025 to September 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.