Skyi Star City, Kirkatwadi

by Skyi Property Ventures LLP. Kirkatwadi, Pune 411024. View on Google Maps

Launched
First of 5 phases
Possession dates (MahaRERA)
Mar 2027 – Dec 2028varies by phase3 of 5 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
42%Mid-construction1 of 5 phases with structure completeWeighted across 5 phases
Units booked
314 of 33693% booked

Project facts

2 BHK173
3 BHK163
Total units336
Buildings5
Land1.2 acres
Phases5
MahaRERA complaints (filed by or against the builder)0

Since Dec 2025: booked 313 → 314

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 5 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Skyi Star City Phase IV
Nearing possession
P5210003427464100%100%
Skyi Star City Phase V
Mid-construction
P521000500996888%100%
Skyi Star City Phase VI
Early stage
P52100053428680%100%
Skyi Star City Phase VII
Mid-construction
P521000534717225%97%
Skyi Star City Phase VIII
Early stage
P52100078694640%69%
Show updates by phase

Skyi Star City Phase IV (P52100034274)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%76%64
100%56%0%64
100%56%0%63
100%17%0%62
100%0%0%62

"—" means MahaRERA shows no figure for that update.

Skyi Star City Phase V (P52100050099)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%88%20%68
100%47%0%68
100%47%0%65
100%29%0%56
100%0%0%58

"—" means MahaRERA shows no figure for that update.

Skyi Star City Phase VI (P52100053428)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%68
100%0%0%61
100%0%0%48
0%0%0%22

"—" means MahaRERA shows no figure for that update.

Skyi Star City Phase VII (P52100053471)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%0%70
100%0%0%69
100%0%0%54
100%0%0%35
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Skyi Star City Phase VIII (P52100078694)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%44
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Skyi Star City is a project by Skyi Property Ventures LLP in Kirkatwadi, Pune 411024, registered with MahaRERA as 5 phases (P52100034274, P52100050099, P52100053428, P52100053471, P52100078694). The first phase was launched in March 2022. Together the phases have 336 units in 5 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 5 phases are active on MahaRERA.

The phases' registered possession dates run from March 2027 to December 2028; 3 of 5 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 42% complete and final finishes 19% complete. 1 of the 5 phases have their structure complete.

314 of the 336 units reported for sale are booked (93%).

Skyi's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA41
Completed without extending the possession date17
Completed after an extension0
Lapsed7
Under construction17
Possession date extended on the builder's application7
Typical time from launch to 100% structure3 years 4 months
MahaRERA complaints (filed by or against the builder), all Skyi projects52 (20 of 41 projects)

See all Skyi projects →

Source: MahaRERA registrations P52100034274, P52100050099, P52100053428, P52100053471 and P52100078694.Open MahaRERA and search P52100034274All projects in Khadakwasla, Kirkatwadi