Skyi Star City, Kirkatwadi
by Skyi Property Ventures LLP. Kirkatwadi, Pune 411024. View on Google Maps
- Launched
- First of 5 phases
- Possession dates (MahaRERA)
- Mar 2027 – Dec 2028varies by phase3 of 5 phases have an extended possession date. Reading a project's possession date
- Concrete structure (RCC)
- 42%Mid-construction1 of 5 phases with structure completeWeighted across 5 phases
- Units booked
- 314 of 33693% booked
Facts
Project facts
| 2 BHK | 173 |
|---|---|
| 3 BHK | 163 |
| Total units | 336 |
| Buildings | 5 |
| Land | 1.2 acres |
| Phases | 5 |
| MahaRERA complaints (filed by or against the builder) | 0 |
Since Dec 2025: booked 313 → 314
Shortlist 2 or more to compare side by side.
Phases
The 5 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Skyi Star City Phase IV Nearing possession | P52100034274 | 64 | 100% | 100% | |
| Skyi Star City Phase V Mid-construction | P52100050099 | 68 | 88% | 100% | |
| Skyi Star City Phase VI Early stage | P52100053428 | 68 | 0% | 100% | |
| Skyi Star City Phase VII Mid-construction | P52100053471 | 72 | 25% | 97% | |
| Skyi Star City Phase VIII Early stage | P52100078694 | 64 | 0% | 69% |
Show updates by phase
Skyi Star City Phase IV (P52100034274)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 76% | 64 | |
| 100% | 56% | 0% | 64 | |
| 100% | 56% | 0% | 63 | |
| 100% | 17% | 0% | 62 | |
| 100% | 0% | 0% | 62 |
"—" means MahaRERA shows no figure for that update.
Skyi Star City Phase V (P52100050099)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 88% | 20% | 68 | |
| 100% | 47% | 0% | 68 | |
| 100% | 47% | 0% | 65 | |
| 100% | 29% | 0% | 56 | |
| 100% | 0% | 0% | 58 |
"—" means MahaRERA shows no figure for that update.
Skyi Star City Phase VI (P52100053428)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 68 | |
| 100% | 0% | 0% | 61 | |
| 100% | 0% | 0% | 48 | |
| 0% | 0% | 0% | 22 |
"—" means MahaRERA shows no figure for that update.
Skyi Star City Phase VII (P52100053471)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 25% | 0% | 70 | |
| 100% | 0% | 0% | 69 | |
| 100% | 0% | 0% | 54 | |
| 100% | 0% | 0% | 35 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Skyi Star City Phase VIII (P52100078694)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 44 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
Skyi Star City is a project by Skyi Property Ventures LLP in Kirkatwadi, Pune 411024, registered with MahaRERA as 5 phases (P52100034274, P52100050099, P52100053428, P52100053471, P52100078694). The first phase was launched in March 2022. Together the phases have 336 units in 5 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 5 phases are active on MahaRERA.
The phases' registered possession dates run from March 2027 to December 2028; 3 of 5 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 42% complete and final finishes 19% complete. 1 of the 5 phases have their structure complete.
314 of the 336 units reported for sale are booked (93%).
Skyi's track record in Pune
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Projects registered with MahaRERA | 41 |
|---|---|
| Completed without extending the possession date | 17 |
| Completed after an extension | 0 |
| Lapsed | 7 |
| Under construction | 17 |
| Possession date extended on the builder's application | 7 |
| Typical time from launch to 100% structure | 3 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Skyi projects | 52 (20 of 41 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and July 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.