Platinum Pallazo Phase II, Chinchwad
by Platinum Square. Chinchwad, Pune 411033. View on Google Maps
- Launched
- 1 year 8 months originally promised
- Possession date (MahaRERA)
- 1 year 2 months awayExtended by 4 years (originally December 2023). Why possession dates change
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- Bookings not reported
Project facts
| 3 BHK | 6 |
|---|---|
| Other units (shops, offices or not given by type) | 1 |
| Total units | 7 |
| Buildings | 1 |
| Complaints on MahaRERA (filed by or against the builder) | 2 |
Since Dec 2025: possession date December 2023 → December 2027 · total units 6 → 7
Construction progress
As reported to MahaRERA at each updateWork not started as of Jul 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Platinum Pallazo Phase II (MahaRERA P52100034326) is a residential project by Platinum Square in Chinchwad, Pune 411033. It was launched in April 2022. It has 7 units in 1 building: 6 homes (3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 4 years from the original December 2023. Construction: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet. Since the December 2025 update, the possession date has moved from December 2023 to December 2027.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.