La Centra, Tathawade
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by M N Landmarks LLP. Tathawade, Pune 411057. View on Google Maps
- Launched
- 4 years 8 months promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 145 of 14799% booked
Project facts
| 2 BHK | 130 |
|---|---|
| Other units (shops, offices or not given by type) | 17 |
| Total units | 147 |
| Buildings | 1 |
| Land | 1.1 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: final finishes 60% → 100%
Compared with 6 similar projects in PIN 411057
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 8 mths | 4 yrs 6 mths |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | December 2026 | January 2027 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 99% | 94% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| TOP Towers - A | April 2022 | June 2026 | 100% | 120 of 154 booked (78%) |
| RGS Forte | April 2022 | March 2027 | 100% | 176 of 185 booked (95%) |
| Park Astra Phase II | May 2022 | December 2026 | 100% | 127 of 136 booked (93%) |
| Kuber Antonia | May 2022 | February 2026 | 100% | 57 of 60 booked (95%) |
| SENSORIUM, Phase VI | May 2022 | September 2026 | 100% | All 258 units booked |
| Ganga Asmi Wing 2 | March 2022 | December 2028 | 28% | 180 of 284 booked (63%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 145 | |
| 100% | 100% | 60% | 145 | |
| 100% | 100% | 0% | 142 | |
| 100% | 100% | 0% | 129 | |
| 100% | 30% | 0% | 120 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
La Centra (MahaRERA P52100034348) is a residential project by M N Landmarks LLP in Tathawade, Pune 411057. It was launched in April 2022. It has 147 units in 1 building: 130 homes (2 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
145 of its 147 units are booked (99%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.