Shaligram Pavillia, Gahunje
by Shaligram Realty LLP. Gahunje, Pune 412101. View on Google Maps
- Launched
- 5 years 8 months promised
- Possession date (MahaRERA)
- 1 year 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 40%Mid-constructionAverage across 5 buildings
- Units booked
- 156 of 22470% booked
Project facts
| 2 BHK | 137 |
|---|---|
| 3 BHK | 67 |
| 4 BHK | 5 |
| 5+ BHK | 1 |
| Other units (shops, offices or not given by type) | 14 |
| Total units | 224 |
| Buildings | 5 |
| Land | 3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 2 |
Since Dec 2025: booked 138 → 156 · complaints 0 → 2
Compared with 6 similar projects in PIN 412101
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 8 mths | 4 yrs 6 mths |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | December 2027 | November 2026 |
| Concrete structure (RCC) complete | 40% | 100% |
| Share of units booked | 70% | 84% |
| Complaints on MahaRERA (filed by or against the builder) | 2 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| The Silver Altair Tower-c | May 2022 | March 2027 | 100% | 116 of 150 booked (77%) |
| Ace Abode Phase 2A | March 2022 | December 2026 | 100% | 271 of 273 booked (99%) |
| Rose Gardenia Phase II | May 2022 | September 2026 | 0% | 42 of 138 booked (30%) |
| Om Mangalam Yash | March 2022 | December 2026 | 100% | 221 of 229 booked (97%) |
| Madhuban | May 2022 | September 2026 | 100% | 143 of 324 booked (44%) |
| City One Skyve | February 2022 | September 2026 | 100% | 327 of 365 booked (90%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 40% | 39% | 156 | |
| 100% | 40% | 39% | 138 | |
| 20% | 20% | 0% | 97 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Shaligram Pavillia (MahaRERA P52100034451) is a residential project by Shaligram Realty LLP in Gahunje, Pune 412101. It was launched in April 2022. It has 224 units in 5 buildings: 210 homes (2, 3, 4 & 5+ BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 5 buildings: excavation complete, structure (RCC) 40% complete, final finishes 39% complete. MahaRERA records do not show it as ready to move in.
156 of its 224 units are booked (70%). Since the December 2025 update, 18 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.