Skip to main content
← Back

City One Skyve, Kiwale

by Shree Sai Capital. Kiwale, Pune 412101. View on Google Maps

Launched
3 years 10 months originally promised
Possession date (MahaRERA)
1 month agoExtended by 9 months (originally December 2025). Why possession dates change
Concrete structure (RCC)
100%Nearing possessionAverage across 3 buildings
Units booked
327 of 36590% booked

Project facts

2 BHK223
3 BHK114
Other units (shops, offices or not given by type)28
Total units365
Buildings3
Land2 acres
Landowner share14
Complaints on MahaRERA (filed by or against the builder)2

Since Dec 2025: booked 316 → 327 · final finishes 63% → 82%

Share on WhatsApp

Compared with 6 similar projects in PIN 412101

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 10 mths4 yrs 7 mths
Possession date extendedBy 9 months2 of 6
Possession date (MahaRERA)September 2026December 2026
Concrete structure (RCC) complete100%92%
Share of units booked90%82%
Complaints on MahaRERA (filed by or against the builder)20

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 10 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 85%Jun 2024: Excavation 90%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 10%Jun 2024: Concrete structure (RCC) 82%Dec 2024: Concrete structure (RCC) 93%Jun 2025: Concrete structure (RCC) 93%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 3%Dec 2024: Final finishes 57%Jun 2025: Final finishes 57%Dec 2025: Final finishes 63%Jul 2026: Final finishes 82%Excavation 100%Concrete structure (RCC) 100%Final finishes 82%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%82%327
100%100%63%316
100%93%57%293
90%82%3%37
85%10%0%37

"—" means MahaRERA shows no figure for that update.

About this project

City One Skyve (MahaRERA P52100033011) is a residential project by Shree Sai Capital in Kiwale, Pune 412101. It was launched in February 2022. It has 365 units in 3 buildings: 337 homes (2 & 3 BHK) and 28 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is September 2026, extended by 9 months from the original December 2025. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 82% complete. MahaRERA records do not show it as ready to move in.

327 of its 365 units are booked (90%). Since the December 2025 update, 11 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100033011.Check it on MahaRERA (P52100033011)All projects in Kiwale, Ravet