The Saga, Pradhikaran
by Nest Saswad Realty LLP. Pradhikaran, Pune 411044. View on Google Maps
- Launched
- 1 year 11 months originally promised
- Possession date (MahaRERA)
- 1 year 7 months ago. No further extension recordedExtended by 1 year (originally March 2024). Why possession dates change
- Concrete structure (RCC)
- 47%Mid-construction
- Units booked
- All booked13 units booked
Project facts
| 4 BHK | 13 |
|---|---|
| Total units | 13 |
| Buildings | 1 |
| Land | 0.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Construction progress
As reported to MahaRERA at each updateConcrete structure (RCC)Final finishesExcavation
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 47% | 0% | 13 | |
| 100% | 47% | 0% | 12 | |
| 100% | 0% | 0% | 12 |
"—" means MahaRERA shows no figure for that update.
About this project
The Saga (MahaRERA P52100035028) is a residential project by Nest Saswad Realty LLP in Pradhikaran, Pune 411044. It was launched in April 2022. It has 13 units in 1 building, with 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in March 2025, after an extension of 1 year from the original March 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 47% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
All 13 units are booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.
Source: MahaRERA registration P52100035028.Check it on MahaRERA (P52100035028)All projects in Pradhikaran, Nigdi