Nyati ERA, Dhanori

by Nyati Construction Private Limited. Dhanori, Pune 411015. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Mar 2026 – Jun 2029varies by phase1 of 3 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
55%Mid-construction1 of 3 phases with structure completeWeighted across 3 phases
Units booked
334 of 74145% booked
Price per sq ft
₹9,7002026 salesup 3% on 2025See what buyers paid

Project facts

1 BHK130
2 BHK282
3 BHK280
Total units749
Buildings12
Land7.8 acres
Phases3
MahaRERA complaints (filed by or against the builder)1

Since Dec 2025: booked 307 → 334

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 810 – 840 sq ft₹74 – 78 lakh2026 sales
3 BHKabout 1,000 – 1,180 sq ft₹1.02 – 1.15 crore2026 sales

Price per sq ft, year by year

2023₹7,800 per sq ft
2024up 3% on 2023₹8,000 per sq ft
2025up 18% on 2024₹9,400 per sq ft
2026up 3% on 2025₹9,700 per sq ft

Studios (under 450 sq ft): ₹4,200 per sq ft in 2026 sales. Sizes about 430 sq ft.

Registered sales across all 3 phases.

Compared with the typical Dhanori rate in 2026: about 5% higher

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Studios are priced separately from flats and are not used in area price comparisons or on the Property rates page.

Why this rate differs from other websites

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Nyati ERA II
Completed
P52100035037120100%7%
Nyati ERA III
Mid-construction Lapsed
P5210004772726096%100%
Nyati ERA IV
Mid-construction
PR12630325001753123%20%
Show updates by phase

Nyati ERA II (P52100035037)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
98%95%63%13
98%94%14%13
95%91%4%10
95%14%0%9

"—" means MahaRERA shows no figure for that update.

Nyati ERA III (P52100047727)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%96%7%260
100%96%7%259
100%79%4%249
100%53%4%247
85%18%0%200

"—" means MahaRERA shows no figure for that update.

Nyati ERA IV (PR1263032500175)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
93%3%0%61
90%0%0%35
0%0%0%12

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

Nyati ERA is a project by Nyati Construction Private Limited in Dhanori, Pune 411015, registered with MahaRERA as 3 phases (P52100035037, P52100047727, PR1263032500175). The first phase was launched in April 2022. Together the phases have 749 units in 12 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed, 1 is lapsed and 1 is active.

The phases' registered possession dates run from March 2026 to June 2029; 1 of 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 55% complete and final finishes 14% complete. 1 of the 3 phases have their structure complete.

334 of the 741 units reported for sale are booked (45%). In 2026 registered sales, 80% of flats here sold at ₹9,700 per sq ft or less (up 3% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 5% higher than the typical Dhanori rate in 2026. Most buyers paid ₹74–78 lakh for 2 BHK flats of about 810–840 sq ft (2026 sales); ₹1.02–1.15 crore for 3 BHK flats of about 1,000–1,180 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra. Its studios (under 450 sq ft) sold at ₹4,200 per sq ft or less in 2026; studios are priced separately from flats.

Source: MahaRERA registrations P52100035037, P52100047727 and PR1263032500175.Open MahaRERA and search P52100035037All projects in Dhanori, Dighi, Vishrantwadi