- Launched
- 3 years 7 months originally promised
- Possession date (MahaRERA)
- 4 months ago. No further extension recordedExtended by 6 months (originally December 2025). What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 48 of 9252% booked
Project facts
| 1 BHK | 4 |
|---|---|
| 2 BHK | 22 |
| 3 BHK | 13 |
| 4 BHK | 1 |
| Other units (shops, offices or not given by type) | 52 |
| Total units | 92 |
| Buildings | 1 |
| Land | 0.3 acres |
| Rehab units | 34 |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: booked 41 → 48 · final finishes 20% → 70% · possession date December 2025 → June 2026
Compared with 6 similar projects in PIN 411038
Projects with 20–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 7 mths | 3 yrs 3 mths |
| Possession date extended | By 6 months | 5 of 6 |
| Possession date passed | Yes, due June 2026 | 2 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 100% | 98% |
| Share of units booked | 52% | 44% |
| Complaints on MahaRERA (filed by or against the builder) | 1 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Snehshilp | May 2022 | December 2026 | 93% | 41 of 54 booked (76%) |
| Tejalkunj No.2 | May 2022 | June 2027 | 95% | 31 of 69 booked (45%) |
| Tungabhadra Co Op Hsg Soc | June 2022 | August 2026 | 100% | 9 of 40 booked (23%) |
| Ratnankur | April 2022 | October 2025 | 100% | 21 of 39 booked (54%) |
| Sneh | April 2022 | December 2027 | 0% | 10 of 37 booked (27%) |
| Ratnaprabha | June 2022 | February 2026 | 100% | 22 of 52 booked (42%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 48 | |
| 100% | 100% | 20% | 41 | |
| 100% | 100% | 0% | 52 | |
| 100% | 54% | 0% | 52 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Laxmikrupa (MahaRERA P52100045252) is a residential project by Gangotree Homes in Kothrud, Pune 411038. It was launched in May 2022. It has 92 units in 1 building: 40 homes (1, 2, 3 & 4 BHK) and 52 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 6 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete. MahaRERA records do not show it as ready to move in.
48 of its 92 units are booked (52%). Since the December 2025 update, 7 more units have been booked and the possession date has moved from December 2025 to June 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.