Chandra Apartment, Kothrud
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Deshpande Landmark Private Limited. Kothrud, Pune 411038. View on Google Maps
- Launched
- 2 years originally promised
- Possession date (MahaRERA)
- 1 year 10 months ago. No further extension recordedExtended by 7 months (originally May 2024). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 6 of 1443% booked
Project facts
| 2 BHK | 7 |
|---|---|
| 3 BHK | 7 |
| Total units | 14 |
| Buildings | 1 |
| Land | 0.1 acres |
| Landowner share | 7 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 6 | |
| 100% | 100% | 80% | 5 | |
| 100% | 100% | 80% | — | |
| 100% | 60% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Chandra Apartment (MahaRERA P52100045316) is a residential project by Deshpande Landmark Private Limited in Kothrud, Pune 411038. It was launched in May 2022. It has 14 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in December 2024, after an extension of 7 months from the original May 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
6 of its 14 units are booked (43%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.