Skip to main content
← Back

RKL Durvankur Jaswand, Alandi

by Lunkad Vishwa Developer. Alandi, Pune 412105. View on Google Maps

Launched
2 years 10 months originally promised
Possession date (MahaRERA)
3 months agoExtended by 1 year 3 months (originally April 2025). Why possession dates change
Concrete structure (RCC)
50%Mid-construction
Units booked
58 of 8073% booked

Project facts

1 BHK44
2 BHK36
Total units80
Buildings1
Land0.5 acres
Landowner share20
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 53 → 58 · possession date April 2025 → July 2026

Share on WhatsApp

Compared with 6 similar projects in PIN 412105

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 10 mths4 yrs 10 mths
Possession date extendedBy 1 year 3 months2 of 6
Possession date (MahaRERA)July 2026June 2027
Concrete structure (RCC) complete50%85%
Share of units booked73%88%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 2 years 10 months have passed
Concrete structure (RCC) 50% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Dec 2023: Concrete structure (RCC) 85%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 100%Jun 2025: Final finishes 100%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 50%Concrete structure (RCC) 50%Final finishes 50%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%50%50%58
50%50%50%53
100%100%100%74
100%100%0%26
100%85%0%7

"—" means MahaRERA shows no figure for that update.

About this project

RKL Durvankur Jaswand (MahaRERA P52100045975) is a residential project by Lunkad Vishwa Developer in Alandi, Pune 412105. It was launched in June 2022. It has 80 units in 1 building, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is July 2026, extended by 1 year 3 months from the original April 2025. Construction: excavation 50% complete, structure (RCC) 50% complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.

58 of its 80 units are booked (73%). Since the December 2025 update, 5 more units have been booked and the possession date has moved from April 2025 to July 2026.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100045975.Check it on MahaRERA (P52100045975)All projects in Charholi, Moshi