Aria A and B, Talegaon Dabhade
by Om Associates · Talegaon Dabhade, Pune 410507 · Map
- Launched
- Jun 20222 yrs 6 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 3 yrs
- Concrete structure
- 6%Mid-construction
- Booked
- 39 of 5768% · 33 in Jul 2026
- Price per sq ft
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 48
- Other units
- 9
- Total units
- 57
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress by tower
From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.
Last 4 updates
| Update | Structure | Finishes |
|---|---|---|
| Sep 2026 | 6% | 96% |
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 6% | 96% | 39 | |
| 100% | 6% | 96% | 33 | |
| 100% | 6% | 96% | 33 | |
| 100% | 6% | 96% | 22 |
"–" means MahaRERA shows no figure for that update.
Construction cost spent
From the engineer's Form 2 filed with MahaRERA.
₹8.2 crore spent · latest estimate ₹8.3 crore · Sep 2026
Spent at each update
| Update | Spent |
|---|---|
| Sep 2026 | ₹8.2 crore |
| Aug 2025 | ₹8.2 crore |
| Jun 2025 | ₹8.2 crore |
| Apr 2025 | ₹8.2 crore |
Other phases of this project
About this project
Aria A and B by Om Associates is a 57-unit project in Talegaon Dabhade, Pune 410507, launched in June 2022 with possession due in December 2027. 39 units booked out of total 57 units. The concrete structure (RCC) is 6% complete.
Read full summary
Aria A and B is a project by Om Associates in Talegaon Dabhade, Pune 410507, registered with MahaRERA as P52100046264. It was launched in June 2022. It has 57 units in 1 building: 48 homes (2 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 3 years from the original December 2024. Construction: excavation complete, structure (RCC) 6% complete, final finishes 96% complete.
39 units booked out of total 57 units (68%). Since the July 2026 update, 6 more units have been booked and the possession date has moved from December 2025 to December 2027.