Aria A and B, Talegaon Dabhade

by Om Associates · Talegaon Dabhade, Pune 410507 · Map

Launched
Jun 20222 yrs 6 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 3 yrs
Concrete structure
6%Mid-construction
Booked
39 of 5768% · 33 in Jul 2026
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
48
Other units
9
Total units
57
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress by tower

From the architect's Form 1 filed with MahaRERA. The last 4 updates per tower.

Last 4 updates
Aria A+B
UpdateStructureFinishes
Sep 20266%96%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%6%96%39
100%6%96%33
100%6%96%33
100%6%96%22

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹8.2 crore spent · latest estimate ₹8.3 crore · Sep 2026

Latest estimate ₹8.3 croreApr 2025: ₹8.2 crore8.2Apr 2025Jun 2025: ₹8.2 crore8.2Jun 2025Aug 2025: ₹8.2 crore8.2Aug 2025Sep 2026: ₹8.2 crore8.2Sep 2026
₹ crore spent
Spent at each update
UpdateSpent
Sep 2026₹8.2 crore
Aug 2025₹8.2 crore
Jun 2025₹8.2 crore
Apr 2025₹8.2 crore

Other phases of this project

About this project

Aria A and B by Om Associates is a 57-unit project in Talegaon Dabhade, Pune 410507, launched in June 2022 with possession due in December 2027. 39 units booked out of total 57 units. The concrete structure (RCC) is 6% complete.

Read full summary

Aria A and B is a project by Om Associates in Talegaon Dabhade, Pune 410507, registered with MahaRERA as P52100046264. It was launched in June 2022. It has 57 units in 1 building: 48 homes (2 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 3 years from the original December 2024. Construction: excavation complete, structure (RCC) 6% complete, final finishes 96% complete.

39 units booked out of total 57 units (68%). Since the July 2026 update, 6 more units have been booked and the possession date has moved from December 2025 to December 2027.