Aria, Talegaon Dabhade

Lapsed

by Om Associates · Talegaon Dabhade, Pune 410507 · Map

Launched
Mar 20212 yrs 3 mths promised
Possession (MahaRERA)
Jun 2023Not extendedWhat does Lapsed mean?
Concrete structure
6%Mid-construction
Booked
24 of 24100%
Price per sq ft
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
16
2 BHK
4
Other units
4
Total units
24
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)6%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 6%Jun 2025: Concrete structure (RCC) 6%Dec 2025: Concrete structure (RCC) 6%Jul 2026: Concrete structure (RCC) 6%Dec 2024: Final finishes 75%Jun 2025: Final finishes 75%Dec 2025: Final finishes 75%Jul 2026: Final finishes 75%Excavation 100%Final finishes 75%Concrete structure (RCC) 6%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%6%75%24
100%6%75%24
100%6%75%24
100%6%75%24

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Other phases of this project

About this project

Aria by Om Associates is a 24-unit project in Talegaon Dabhade, Pune 410507, launched in March 2021; its MahaRERA registration has lapsed. 24 units booked out of total 24 units. The concrete structure (RCC) is 6% complete.

Read full summary

Aria is a project by Om Associates in Talegaon Dabhade, Pune 410507, registered with MahaRERA as P52100028512. It was launched in March 2021. It has 24 units in 1 building: 20 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 6% complete, final finishes 75% complete.

24 units booked out of total 24 units (100%).