Yashwin Enchante, Wagholi

by Vilas Javdekar Infinitee Developers Pvt. Ltd.. Wagholi, Pune 412207. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Jun 2027 – Dec 2029varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
62%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
Units booked
1,787 of 2,04188% booked
Price per sq ft
₹11,2002026 salesup 11% on 2025See what buyers paid

Project facts

2 BHK1,073
3 BHK773
Total units2,041
Buildings11
Land5.4 acres
Phases2
MahaRERA complaints (filed by or against the builder)1

Since Dec 2025: booked 1,235 → 1,787

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 720 – 850 sq ft₹78 – 94 lakh2026 sales
3 BHKabout 910 sq ft₹82 – 84 lakh2025 sales
4 BHKabout 1,400 – 1,430 sq ft₹1.16 – 1.22 crore2023 sales

Price per sq ft, year by year

2023₹8,500 per sq ft
2024up 6% on 2023₹9,000 per sq ft
2025up 12% on 2024₹10,100 per sq ft
2026up 11% on 2025₹11,200 per sq ft

Registered sales across all 2 phases.

Compared with the typical Wagholi rate in 2026: about 10% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Yashwin Enchante Phase 1
Nearing possession
P52100046510853100%94%
Yashwin Enchante Phase 2
Mid-construction
P5210007745599330%82%
Show updates by phase

Yashwin Enchante Phase 1 (P52100046510)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%887
100%100%68%887
100%96%0%886
100%86%0%885
100%31%0%878

"—" means MahaRERA shows no figure for that update.

Yashwin Enchante Phase 2 (P52100077455)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
82%30%0%900
98%2%0%348
26%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Yashwin Enchante is a project by Vilas Javdekar Infinitee Developers Pvt. Ltd. in Wagholi, Pune 412207, registered with MahaRERA as 2 phases (P52100046510, P52100077455). The first phase was launched in August 2022. Together the phases have 2,041 units in 11 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The phases' registered possession dates run from June 2027 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 62% complete and final finishes 37% complete. 1 of the 2 phases have their structure complete.

1,787 of the 2,041 units reported for sale are booked (88%). In 2026 registered sales, 80% of flats here sold at ₹11,200 per sq ft or less (up 11% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 10% lower than the typical Wagholi rate in 2026. Most buyers paid ₹78–94 lakh for 2 BHK flats of about 720–850 sq ft (2026 sales); ₹82–84 lakh for 3 BHK flats of about 910 sq ft (2025 sales); ₹1.16–1.22 crore for 4 BHK flats of about 1,400–1,430 sq ft (2023 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Vilas Javdekar's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA45
Completed without extending the possession date25
Completed after an extension1
Lapsed0
Under construction19
Possession date extended on the builder's application1
Typical time from launch to 100% structure2 years 10 months
MahaRERA complaints (filed by or against the builder), all Vilas Javdekar projects27 (19 of 45 projects)

See all Vilas Javdekar projects →

Source: MahaRERA registrations P52100046510 and P52100077455.Open MahaRERA and search P52100046510All projects in Wagholi