Skip to main content
← Back

Yash Nanda, Peth Areas

by Yashanand Developers. Peth Areas, Pune 411002. View on Google Maps

Launched
2 years 11 months originally promised
Possession date (MahaRERA)
9 months awayExtended by 2 years (originally July 2025). Why possession dates change
Concrete structure (RCC)
90%Mid-construction
Units booked
8 of 2928% booked

Project facts

1 RK14
1 BHK2
2 BHK2
3 BHK4
Other units (shops, offices or not given by type)7
Total units29
Buildings1
Land0.2 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 10 → 8 · total units 27 → 29

Share on WhatsApp

Compared with 4 similar projects in PIN 411002

Projects with up to 20 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 411002
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 11 mths3 yrs 11 mths
Possession date extendedBy 2 years1 of 4
Possession date (MahaRERA)July 2027March 2027
Concrete structure (RCC) complete90%100%
Share of units booked28%25%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 2 years 11 months have passed
Concrete structure (RCC) 90% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 40%Jun 2024: Concrete structure (RCC) 70%Dec 2024: Concrete structure (RCC) 90%Jun 2025: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 20%Jul 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 90%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%20%8
100%90%20%10
100%90%0%10
100%70%0%—
100%40%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Yash Nanda (MahaRERA P52100046523) is a residential project by Yashanand Developers in Peth Areas, Pune 411002. It was launched in August 2022. It has 29 units in 1 building: 22 homes (1 RK, 1 BHK, 2 BHK & 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is July 2027, extended by 2 years from the original July 2025. Construction: excavation complete, structure (RCC) 90% complete, final finishes 20% complete. MahaRERA records do not show it as ready to move in.

8 of its 29 units are booked (28%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100046523.Check it on MahaRERA (P52100046523)All projects in Peth Areas