Basil Chandrakant, Ambegaon Budruk
by Shree Sadguru Developers. Ambegaon Budruk, Pune 411046. View on Google Maps
- Launched
- 3 years 9 months promised
- Possession date (MahaRERA)
- 3 months agoPossession date unchanged since launch
- Concrete structure (RCC)
- 55%Mid-constructionAverage across 2 buildings
- Units booked
- 120 of 20359% booked
Project facts
| 1 BHK | 19 |
|---|---|
| 2 BHK | 106 |
| 3 BHK | 8 |
| Other units (shops, offices or not given by type) | 70 |
| Total units | 203 |
| Buildings | 2 |
| Land | 1.1 acres |
| Landowner share | 82 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 115 → 120 · final finishes 10% → 50%
Compared with 3 similar projects in PIN 411046
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 9 mths | 2 yrs 7 mths |
| Possession date extended | No | 2 of 3 |
| Possession date (MahaRERA) | July 2026 | December 2028 |
| Concrete structure (RCC) complete | 55% | 100% |
| Share of units booked | 59% | 53% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| One Residency Phase 1 | October 2022 | December 2025 | 100% | 137 of 138 booked (99%) |
| Chandrangan Revanta | November 2022 | December 2028 | 75% | 51 of 207 booked (25%) |
| Nandanvan Colina | February 2023 | February 2026 | 100% | 42 of 79 booked (53%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 55% | 50% | 120 | |
| 100% | 55% | 10% | 115 | |
| 100% | 55% | 10% | 185 | |
| 100% | 48% | 0% | 168 | |
| 100% | 0% | 0% | 10 |
"—" means MahaRERA shows no figure for that update.
About this project
Basil Chandrakant (MahaRERA P52100047305) is a residential project by Shree Sadguru Developers in Ambegaon Budruk, Pune 411046. It was launched in October 2022. It has 203 units in 2 buildings: 133 homes (1, 2 & 3 BHK) and 70 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is July 2026, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 55% complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.
120 of its 203 units are booked (59%). Since the December 2025 update, 5 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.