Nandanvan Colina, Ambegaon Budruk
Lapsed
by Sai Sankalp Developers. Ambegaon Budruk, Pune 411046. View on Google Maps
- Launched
- 2 years 6 months originally promised
- Possession date (MahaRERA)
- 8 months ago. No further extension recordedExtended by 6 months (originally August 2025). What "Lapsed" means
- Concrete structure (RCC)
- 100%Nearing possession
- Units booked
- 42 of 7953% booked
Project facts
| 1 BHK | 13 |
|---|---|
| 2 BHK | 59 |
| Other units (shops, offices or not given by type) | 7 |
| Total units | 79 |
| Buildings | 1 |
| Land | 0.5 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 30 → 42 · structure 62% → 100% · final finishes 0% → 60%
Compared with 6 similar projects in PIN 411046
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 6 mths | 4 yrs 2 mths |
| Possession date extended | By 6 months | 2 of 6 |
| Possession date passed | Yes, due February 2026 | 1 ready to move; 1 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 53% | 46% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shivay Construction | March 2023 | December 2025 | 100% | 32 of 68 booked (47%) |
| Padmashree Phase - I | January 2023 | December 2027 | 100% | 15 of 44 booked (34%) |
| Talav Sangam | May 2023 | December 2027 | 100% | 6 of 40 booked (15%) |
| Wisteria | May 2023 | December 2027 | 100% | 59 of 130 booked (45%) |
| Basil Chandrakant | October 2022 | July 2026 | 55% | 120 of 203 booked (59%) |
| One Residency Phase 1 | October 2022 | December 2025 | 100% | 137 of 138 booked (99%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 60% | 42 | |
| 100% | 62% | 0% | 30 | |
| 100% | 62% | 0% | 7 | |
| 100% | 62% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Nandanvan Colina (MahaRERA P52100049350) is a residential project by Sai Sankalp Developers in Ambegaon Budruk, Pune 411046. It was launched in February 2023. It has 79 units in 1 building: 72 homes (1 & 2 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in February 2026, after an extension of 6 months from the original August 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete. MahaRERA records do not show it as ready to move in.
42 of its 79 units are booked (53%). Since the December 2025 update, 12 more units have been booked and the reported concrete structure (RCC) has gone from 62% to 100%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.