Shree Saai Forrtune, Moshi

by Mrunali Realty LLP. Moshi, Pune 412105. View on Google Maps

Launched
4 years 2 months originally promised
Possession date (MahaRERA)
1 year 2 months awayExtended by 1 year (originally December 2026). Why possession dates change
Concrete structure (RCC)
40%Mid-constructionAverage across 3 buildings
Units booked
118 of 28142% booked

Project facts

2 BHK158
3 BHK74
Other units (shops, offices or not given by type)49
Total units281
Buildings3
Land2.2 acres
Landowner share13
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 90 → 118 · structure 33% → 40% · final finishes 0% → 17% · total units 262 → 281

Share on WhatsApp

Compared with 6 similar projects in PIN 412105

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 2 mths3 yrs 8 mths
Possession date extendedBy 1 year2 of 6
Possession date (MahaRERA)December 2027December 2026
Concrete structure (RCC) complete40%100%
Share of units booked42%89%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years of the originally promised 4 years 2 months have passed
Concrete structure (RCC) 40% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 33%Jul 2026: Excavation 67%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 60%Dec 2024: Concrete structure (RCC) 60%Jun 2025: Concrete structure (RCC) 60%Dec 2025: Concrete structure (RCC) 33%Jul 2026: Concrete structure (RCC) 40%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 17%Excavation 67%Concrete structure (RCC) 40%Final finishes 17%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%40%17%118
33%33%0%90
100%60%0%97
100%0%0%15

"—" means MahaRERA shows no figure for that update.

About this project

Shree Saai Forrtune (MahaRERA P52100047346) is a residential project by Mrunali Realty LLP in Moshi, Pune 412105. It was launched in October 2022. It has 281 units in 3 buildings: 232 homes (2 & 3 BHK) and 49 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 1 year from the original December 2026. Construction, averaged across its 3 buildings: excavation 67% complete, structure (RCC) 40% complete, final finishes 17% complete. MahaRERA records do not show it as ready to move in.

118 of its 281 units are booked (42%). Since the December 2025 update, 28 more units have been booked and the reported concrete structure (RCC) has gone from 33% to 40%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100047346.Check it on MahaRERA (P52100047346)All projects in Charholi, Moshi