Skip to main content
← Back

Gandharv Nagari A6, Moshi

Lapsed

by Vinayak Pandharinath Bhongale. Moshi, Pune 412105. View on Google Maps

Launched
1 year 11 months originally promised
Possession date (MahaRERA)
1 year ago. No further extension recordedExtended by 1 year (originally October 2024). What "Lapsed" means
Concrete structure (RCC)
100%Nearing possession
Units booked
11 of 1385% booked

Project facts

2 BHK10
Other units (shops, offices or not given by type)3
Total units13
Buildings1
Land0.6 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 7 → 11 · final finishes 0% → 25%

Share on WhatsApp

Compared with 4 similar projects in PIN 412105

Projects with up to 20 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)1 yr 11 mths2 yrs 6 mths
Possession date extendedBy 1 year1 of 4
Possession date passedYes, due October 20251 ready to move; 1 also past their date
Concrete structure (RCC) complete100%32%
Share of units booked85%50%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 1 year 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 16%Dec 2024: Concrete structure (RCC) 20%Jun 2025: Concrete structure (RCC) 20%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 100%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%11
100%100%0%7
100%20%0%3
100%16%0%3
100%0%0%3

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Gandharv Nagari A6 (MahaRERA P52100047726) is a residential project by Vinayak Pandharinath Bhongale in Moshi, Pune 412105. It was launched in November 2022. It has 13 units in 1 building: 10 homes (2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in October 2025, after an extension of 1 year from the original October 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete. MahaRERA records do not show it as ready to move in.

11 of its 13 units are booked (85%). Since the December 2025 update, 4 more units have been booked.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100047726.Check it on MahaRERA (P52100047726)All projects in Charholi, Moshi