Shivvihar Phase 2, Charholi Khurd
Finishing stage
Final finishes 97% · completion not yet filed on MahaRERA
by Royal Construction. Charholi Khurd, Pune 412105. View on Google Maps
- Launched
- 3 years 1 month originally promised
- Possession date (MahaRERA)
- 2 months awayExtended by 1 year (originally December 2025). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 35 of 6058% booked
Project facts
| 1 BHK | 49 |
|---|---|
| 2 BHK | 7 |
| Other units (shops, offices or not given by type) | 4 |
| Total units | 60 |
| Name as registered on MahaRERA | SHIVVIHARPHASE2 |
| Buildings | 1 |
| Land | 0.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 90% → 100% · final finishes 0% → 97% · possession date December 2025 → December 2026
Compared with 5 similar projects in PIN 412105
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 1 mth | 3 yrs 11 mths |
| Possession date extended | By 1 year | 1 of 5 |
| Possession date (MahaRERA) | December 2026 | June 2027 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 58% | 98% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vijay Capital | November 2022 | December 2027 | 50% | Bookings not reported |
| Destination 24 Avenue B Building | November 2022 | March 2026 | 100% | 20 of 118 booked (17%) |
| L Axis Phase III Cluster A | October 2022 | July 2028 | 67% | All 96 units booked |
| Gandharv Mithila Building A Wing C | January 2023 | December 2026 | 100% | All 56 units booked |
| Gandharv Mithila Building A Wing A, B | January 2023 | December 2026 | 100% | 53 of 56 booked (95%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 97% | 35 | |
| 100% | 90% | 0% | 35 | |
| 100% | 90% | 0% | 12 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Shivvihar Phase 2 (MahaRERA P52100047842) is a residential project by Royal Construction in Charholi Khurd, Pune 412105. It was launched in November 2022. It has 60 units in 1 building: 56 homes (1 & 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 97% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
35 of its 60 units are booked (58%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 90% to 100% and the possession date has moved from December 2025 to December 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.