Skip to main content
← Back

Swastika, Market Yard

by Vikram Ram Agarwal. Market Yard, Pune 411037. View on Google Maps

Launched
4 years promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possession
Units booked
106 of 11691% booked

Project facts

2 BHK39
3 BHK69
4 BHK2
Other units (shops, offices or not given by type)6
Total units116
Buildings1
Land0.8 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 104 → 106 · structure 80% → 100% · final finishes 0% → 15% · total units 115 → 116

Share on WhatsApp

Compared with 4 similar projects in PIN 411037

Projects with 50–250 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 411037
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs4 yrs 4 mths
Possession date extendedNo1 of 4
Possession date (MahaRERA)December 2026June 2027
Concrete structure (RCC) complete100%18%
Share of units booked91%34%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 10 months of the promised 4 years have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 40%Jun 2025: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 15%Excavation 100%Concrete structure (RCC) 100%Final finishes 15%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%15%106
100%80%0%104
100%40%0%78
100%0%0%24
100%0%0%20

"—" means MahaRERA shows no figure for that update.

About this project

Swastika (MahaRERA P52100048349) is a residential project by Vikram Ram Agarwal in Market Yard, Pune 411037. It was launched in December 2022. It has 116 units in 1 building: 110 homes (2, 3 & 4 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 15% complete. MahaRERA records do not show it as ready to move in.

106 of its 116 units are booked (91%). Since the December 2025 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 80% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100048349.Check it on MahaRERA (P52100048349)All projects in Gultekdi, Bibwewadi