Skip to main content
← Back

Panchtatva, Gultekdi

by Sanskruti Pinnacle. Gultekdi, Pune 411037. View on Google Maps

Launched
4 years originally promised
Possession date (MahaRERA)
2 months awayExtended by 8 months (originally April 2026). Why possession dates change
Concrete structure (RCC)
67%Mid-constructionAverage across 3 buildings
Units booked
81 of 13361% booked

Project facts

2 BHK117
3 BHK16
Total units133
Buildings3
Land1.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 64 → 81 · structure 51% → 67% · final finishes 0% → 65% · possession date April 2026 → December 2026 · total units 216 → 133

Share on WhatsApp

Compared with 4 similar projects in PIN 411037

Projects with 60–300 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 411037
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs4 yrs
Possession date extendedBy 8 months2 of 4
Possession date (MahaRERA)December 2026December 2026
Concrete structure (RCC) complete67%90%
Share of units booked61%68%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years have passed
Concrete structure (RCC) 67% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 67%Jun 2024: Excavation 67%Dec 2024: Excavation 67%Jun 2025: Excavation 67%Dec 2025: Excavation 67%Jul 2026: Excavation 67%Dec 2023: Concrete structure (RCC) 47%Jun 2024: Concrete structure (RCC) 51%Dec 2024: Concrete structure (RCC) 51%Jun 2025: Concrete structure (RCC) 51%Dec 2025: Concrete structure (RCC) 51%Jul 2026: Concrete structure (RCC) 67%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 65%Excavation 67%Concrete structure (RCC) 67%Final finishes 65%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%67%65%81
67%51%0%64
67%47%0%59

"—" means MahaRERA shows no figure for that update.

About this project

Panchtatva (MahaRERA P52100034555) is a residential project by Sanskruti Pinnacle in Gultekdi, Pune 411037. It was launched in April 2022. It has 133 units in 3 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 8 months from the original April 2026. Construction, averaged across its 3 buildings: excavation 67% complete, structure (RCC) 67% complete, final finishes 65% complete. MahaRERA records do not show it as ready to move in.

81 of its 133 units are booked (61%). Since the December 2025 update, 17 more units have been booked, the reported concrete structure (RCC) has gone from 51% to 67% and the possession date has moved from April 2026 to December 2026.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100034555.Check it on MahaRERA (P52100034555)All projects in Gultekdi, Bibwewadi