SkyHigh Towers D4, Maan
by New World Landmark LLP. Maan, Pune 411057. View on Google Maps
- Launched
- 5 years 11 months originally promised
- Possession date (MahaRERA)
- 3 years 2 months awayExtended by 1 year (originally December 2028). Why possession dates change
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- Bookings not reported
Project facts
| 1 RK | 7 |
|---|---|
| 1 BHK | 2 |
| 2 BHK | 151 |
| Total units | 160 |
| Buildings | 1 |
| Land | 8.4 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 6 similar projects in PIN 411057
Projects with 70–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 11 mths | 4 yrs 7 mths |
| Possession date extended | By 1 year | 2 of 6 |
| Possession date (MahaRERA) | December 2029 | December 2027 |
| Concrete structure (RCC) complete | 0% | 100% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Life Republic/Sector R10/10th Avenue/Universe/Phase V | January 2023 | December 2027 | 100% | 290 of 295 booked (98%) |
| Fusion Towers Phase IV | February 2023 | December 2026 | 100% | 132 of 175 booked (75%) |
| Apostrophe Hinjawadi Tower B | December 2022 | December 2027 | 100% | Bookings not reported |
| Building B2 Eon Homes | December 2022 | December 2027 | 0% | 143 of 183 booked (78%) |
| Livmo Phase II | February 2023 | December 2025 | 100% | 150 of 196 booked (77%) |
| VTP Bellissimo Phase 3 | December 2022 | March 2027 | 35% | 143 of 208 booked (69%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
SkyHigh Towers D4 (MahaRERA P52100048403) is a residential project by New World Landmark LLP in Maan, Pune 411057. It was launched in January 2023. It has 160 units in 1 building, with 1 RK, 1 BHK & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, extended by 1 year from the original December 2028. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.