Magnus Parkway, Kiwale
by Siddhivinayak Landmarks. Kiwale, Pune 412101. View on Google Maps
- Launched
- 4 years 11 months promised
- Possession date (MahaRERA)
- 1 year 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 79%Mid-constructionAverage across 4 buildings
- Units booked
- 225 of 39158% booked
Project facts
| 1 BHK | 8 |
|---|---|
| 2 BHK | 228 |
| 3 BHK | 76 |
| Other units (shops, offices or not given by type) | 79 |
| Total units | 391 |
| Buildings | 4 |
| Land | 2.4 acres |
| Landowner share | 128 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 208 → 225 · structure 53% → 79%
Compared with 6 similar projects in PIN 412101
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 11 mths | 4 yrs |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | December 2027 | December 2026 |
| Concrete structure (RCC) complete | 79% | 90% |
| Share of units booked | 58% | 57% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Gini Vibrance | January 2023 | December 2026 | 100% | All 180 units booked |
| Sparkle at Godrej Serene | January 2023 | December 2027 | 0% | Bookings not reported |
| Basil Flora | December 2022 | March 2027 | 52% | 128 of 342 booked (37%) |
| Little Earth, Kiwale Building C10 and C11 | December 2022 | December 2026 | 100% | 135 of 346 booked (39%) |
| Maithili Aroma | February 2023 | December 2026 | 80% | 161 of 266 booked (61%) |
| Laxmi Empire | December 2022 | December 2026 | 100% | 219 of 385 booked (57%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 79% | 0% | 225 | |
| 100% | 53% | 0% | 208 | |
| 100% | 8% | 0% | 132 | |
| 100% | 0% | 0% | 93 | |
| 90% | 0% | 0% | 39 |
"—" means MahaRERA shows no figure for that update.
About this project
Magnus Parkway (MahaRERA P52100048433) is a residential project by Siddhivinayak Landmarks in Kiwale, Pune 412101. It was launched in January 2023. It has 391 units in 4 buildings: 312 homes (1, 2 & 3 BHK) and 79 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) 79% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
225 of its 391 units are booked (58%). Since the December 2025 update, 17 more units have been booked and the reported concrete structure (RCC) has gone from 53% to 79%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.