Skip to main content
← Back

Maithili Aroma, Ravet

by Marne Group. Ravet, Pune 412101. View on Google Maps

Launched
3 years 10 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
80%Mid-constructionAverage across 9 buildings
Units booked
161 of 26661% booked
Price per sq ft (incl. balconies and terrace)
₹7,8002026 so far · 19 salesup 8% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK4
1 BHK70
2 BHK162
3 BHK28
5+ BHK2
Total units266
Buildings9
Land1.4 acres
Landowner share14
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 79 → 161 · structure 32% → 80% · final finishes 0% → 27% · total units 223 → 266

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
700 – 800 sq ft₹51 – 59 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹6,900 per sq ft39 sales
2025up 4% on 2024₹7,200 per sq ft48 sales
2026 so farup 8% on 2025₹7,800 per sq ft19 sales

Rate vs other Ravet projects, 2026: about 15% lower

Compared with 6 similar projects in PIN 412101

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412101
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 10 mths4 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2026July 2027
Concrete structure (RCC) complete80%100%
Share of units booked61%58%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 8 months of the promised 3 years 10 months have passed
Concrete structure (RCC) 80% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 78%Jun 2024: Excavation 78%Dec 2024: Excavation 78%Jun 2025: Excavation 78%Dec 2025: Excavation 78%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 23%Jun 2024: Concrete structure (RCC) 23%Dec 2024: Concrete structure (RCC) 32%Jun 2025: Concrete structure (RCC) 32%Dec 2025: Concrete structure (RCC) 32%Jul 2026: Concrete structure (RCC) 80%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 27%Excavation 100%Concrete structure (RCC) 80%Final finishes 27%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%27%161
78%32%0%79
78%23%0%56
78%23%0%25

"—" means MahaRERA shows no figure for that update.

About this project

Maithili Aroma (MahaRERA P52100049541) is a residential project by Marne Group in Ravet, Pune 412101. It was launched in February 2023. It has 266 units in 9 buildings, with 1 RK, 1 BHK, 2 BHK, 3 BHK & 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction, averaged across its 9 buildings: excavation complete, structure (RCC) 80% complete, final finishes 27% complete. MahaRERA records do not show it as ready to move in.

161 of its 266 units are booked (61%). Since the December 2025 update, 82 more units have been booked and the reported concrete structure (RCC) has gone from 32% to 80%. 80% of the 2026 (so far) sales we found here were at ₹7,800 per sq ft or less (up 8% on 2025), counting balconies and terrace in the size, based on 19 registered sales. Buyers here paid a rate about 15% lower than at other Ravet projects in 2026. Most buyers paid ₹51–59 lakh for flats of 700–800 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100049541.Check it on MahaRERA (P52100049541)All projects in Kiwale, Ravet