- Launched
- 2 years 4 months originally promised
- Possession date (MahaRERA)
- 11 months ago. No further extension recordedExtended by 6 months (originally May 2025). What "Lapsed" means
- Concrete structure (RCC)
- 78%Mid-constructionAverage across 4 buildings
- Units booked
- 48 of 7069% booked
Project facts
| 2 BHK | 56 |
|---|---|
| 3 BHK | 14 |
| Total units | 70 |
| Buildings | 4 |
| Land | 0.5 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 45 → 48 · structure 43% → 78% · final finishes 0% → 73%
Compared with 6 similar projects in PIN 412101
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 4 mths | 3 yrs 6 mths |
| Possession date extended | By 6 months | 3 of 6 |
| Possession date passed | Yes, due November 2025 | 3 ready to move; 1 also past their date |
| Concrete structure (RCC) complete | 78% | 100% |
| Share of units booked | 69% | 86% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Primrose Park | January 2023 | December 2026 | 100% | 66 of 107 booked (62%) |
| Om Mangalam Disha | January 2023 | September 2026 | 100% | 104 of 130 booked (80%) |
| Krishna Kunj | January 2023 | December 2027 | 100% | All 38 units booked |
| The Silver Altair Tower-D MHADA | February 2023 | July 2025 | 100% | All 48 units booked |
| K Ville Phase IV | February 2023 | December 2026 | 100% | 127 of 140 booked (91%) |
| Midori Towers | October 2022 | December 2025 | 88% | 42 of 65 booked (65%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 78% | 73% | 48 | |
| 75% | 43% | 0% | 45 | |
| 75% | 43% | 0% | 32 | |
| 50% | 20% | 0% | 10 |
"—" means MahaRERA shows no figure for that update.
About this project
GT Pride (MahaRERA P52100048595) is a residential project by G T Associates in Ravet, Pune 412101. It was launched in January 2023. It has 70 units in 4 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in November 2025, after an extension of 6 months from the original May 2025. That date has passed and no further extension has been recorded. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) 78% complete, final finishes 73% complete. MahaRERA records do not show it as ready to move in.
48 of its 70 units are booked (69%). Since the December 2025 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 43% to 78%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.