- Launched
- 2 years 11 months promised
- Possession date (MahaRERA)
- 10 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 50%Mid-constructionAverage across 2 buildings
- Units booked
- 37 of 4093% booked
Project facts
| 2 BHK | 39 |
|---|---|
| 3 BHK | 1 |
| Total units | 40 |
| Buildings | 2 |
| Land | 0.6 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 33 → 37
Construction progress
As reported to MahaRERA at each updateConcrete structure (RCC)Final finishesExcavation
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 50% | 50% | 37 | |
| 50% | 50% | 50% | 33 | |
| 50% | 50% | 50% | 22 | |
| 50% | 50% | 40% | 9 | |
| 50% | 50% | 0% | 7 |
"—" means MahaRERA shows no figure for that update.
About this project
Shivkamal (MahaRERA P52100048622) is a residential project by Prapti Associates in Dighi, Pune 411015. It was launched in January 2023. It has 40 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction, averaged across its 2 buildings: excavation 50% complete, structure (RCC) 50% complete, final finishes 50% complete. MahaRERA records do not show it as ready to move in.
37 of its 40 units are booked (93%). Since the December 2025 update, 4 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.
Source: MahaRERA registration P52100048622.Check it on MahaRERA (P52100048622)All projects in Dhanori, Dighi, Vishrantwadi