Sumit Homes, Dhayari
by Sumit Homes. Dhayari, Pune 411041. View on Google Maps
- Launched
- 5 years 9 months promised
- Possession date (MahaRERA)
- 2 years awayPossession date unchanged since launch
- Concrete structure (RCC)
- 48%Mid-constructionAverage across 2 buildings
- Units booked
- Bookings not reported
Project facts
| 1 BHK | 28 |
|---|---|
| 2 BHK | 26 |
| Total units | 54 |
| Buildings | 2 |
| Land | 0.5 acres |
| Landowner share | 8 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 6% → 48%
Compared with 5 similar projects in PIN 411041
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 9 mths | 4 yrs 9 mths |
| Possession date extended | No | 2 of 5 |
| Possession date (MahaRERA) | October 2028 | December 2027 |
| Concrete structure (RCC) complete | 48% | 90% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Devanshi | January 2023 | December 2026 | 90% | 6 of 29 booked (21%) |
| Nakshatra | March 2023 | December 2027 | 100% | 30 of 34 booked (88%) |
| Park Life Wing C | April 2023 | March 2028 | 100% | 48 of 89 booked (54%) |
| Vasant Vihar A Wing | June 2023 | September 2026 | 5% | 8 of 40 booked (20%) |
| Abhiruchi MHADA 3 | June 2023 | May 2028 | 90% | 58 of 110 booked (53%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 48% | 0% | — | |
| 50% | 6% | 0% | — | |
| 23% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Sumit Homes (MahaRERA P52100048874) is a residential project by Sumit Homes in Dhayari, Pune 411041. It was launched in January 2023. It has 54 units in 2 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is October 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation 50% complete, structure (RCC) 48% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet. Since the December 2025 update, the reported concrete structure (RCC) has gone from 6% to 48%.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.