Urban Homes A Wing, Charholi
Finishing stageLapsed
Final finishes 100% · completion not yet filed on MahaRERA
by Lotus Properties. Charholi, Pune 412105. View on Google Maps
- Launched
- 3 years 2 months promised
- Possession date (MahaRERA)
- 7 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 69 of 11361% booked
Project facts
| 1 BHK | 40 |
|---|---|
| 2 BHK | 56 |
| 3 BHK | 14 |
| Other units (shops, offices or not given by type) | 3 |
| Total units | 113 |
| Buildings | 1 |
| Land | 1.1 acres |
| Landowner share | 18 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 55 → 69 · final finishes 1% → 100%
Compared with 6 similar projects in PIN 412105
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 2 mths | 3 yrs 11 mths |
| Possession date extended | No | 1 of 6 |
| Possession date passed | Yes, due March 2026 | 5 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 61% | 90% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Gandharv Nagari Building A3 Wing A, B | January 2023 | September 2026 | 100% | 88 of 98 booked (90%) |
| Gandharv Mithila Building A Wing C | January 2023 | December 2026 | 100% | All 56 units booked |
| Gandharv Mithila Building A Wing A, B | January 2023 | December 2026 | 100% | 53 of 56 booked (95%) |
| Divine City - Phase I - Building B | January 2023 | February 2027 | 20% | Bookings not reported |
| Vrinda | January 2023 | March 2027 | 100% | 170 of 242 booked (70%) |
| Gandharv Mithila Building A Wing E, F, G | February 2023 | December 2026 | 100% | 72 of 98 booked (73%) |
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 69 | |
| 100% | 100% | 1% | 55 | |
| 100% | 79% | 1% | 35 | |
| 100% | 46% | 10% | 28 | |
| 100% | 20% | 10% | 17 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Urban Homes A Wing (MahaRERA P52100048902) is a residential project by Lotus Properties in Charholi, Pune 412105. It was launched in January 2023. It has 113 units in 1 building: 110 homes (1, 2 & 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in March 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
69 of its 113 units are booked (61%). Since the December 2025 update, 14 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.