Raman Stellar, Tathawade

Ready to move

by Soham Shivam Developers · Tathawade, Pune 411033 · Map

Launched
Feb 20232 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Ready to move
Booked
85 of 11475% · 61 in Jul 2026
Price per sq ft
₹9,0002026 sales
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid

Registered sales, not today's asking price.

TypeSize, sq ftMost paidYear
1 RK / 1 BHK470₹39–42 lakh2024
2 BHK730–750₹46–58 lakh2026
2 BHK780₹67–71 lakh2026

Price per sq ft, year by year

YearPrice per sq ftOn previous year
2026 · no 2025 sales₹9,000–
2024₹8,300–

About 15% below the typical Tathawade rate in 2026.

How to read this price
  • Price per sq ft is the typical rate in that year's registered sales.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

Project facts

1 BHK
14
2 BHK
98
Other units
2
Total units
114
Buildings
4
Land
0.9 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Oct 2026Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Jun 2025: Final finishes 8%Dec 2025: Final finishes 35%Jul 2026: Final finishes 35%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%85
100%100%35%61
100%100%35%61
100%100%8%57

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Construction cost spent

From the engineer's Form 2 filed with MahaRERA.

₹17.7 crore spent · latest estimate ₹17.9 crore · Oct 2026

Latest estimate ₹17.9 croreJan 2024: ₹2.8 crore2.8Jan 2024Oct 2026: ₹17.7 crore17.7Oct 2026
₹ crore spent

The builder raised the estimate from ₹9.1 crore to ₹17.9 crore in Oct 2026.

Spent at each update
UpdateSpent
Oct 2026₹17.7 crore
Jan 2024₹2.8 crore

Compared with 6 similar projects in PIN 411033

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths4 yrs
Possession date extendedBy 1 yr3 of 6
Possession date (MahaRERA)Dec 2026Mar 2027
Concrete structure (RCC)100%92%
Units booked75%81%
MahaRERA complaints (filed by or against the builder)00

The 6 projects, latest price per sq ft

Other phases of this project are not included in the similar projects.

About this project

Raman Stellar by Soham Shivam Developers is a 114-unit project in Tathawade, Pune 411033, launched in February 2023 with possession due in December 2026. 85 units booked out of total 114 units. Typical rate: ₹9,000 per sq ft (2026 registered sales).

Read full summary

Raman Stellar is a project by Soham Shivam Developers in Tathawade, Pune 411033, registered with MahaRERA as P52100049189. It was launched in February 2023. It has 114 units in 4 buildings: 112 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

85 units booked out of total 114 units (75%). Since the July 2026 update, 24 more units have been booked and the possession date has moved from December 2025 to December 2026. In 2026 registered sales, the typical rate here was ₹9,000 per sq ft, counting balconies and terrace in the size. Buyers here paid a rate about 15% lower than the typical Tathawade rate in 2026. Most buyers paid ₹39–42 lakh for 1 RK / 1 BHK flats of about 470 sq ft (2024 sales); ₹46–58 lakh for 2 BHK flats of about 730–750 sq ft (2026 sales); ₹67–71 lakh for 2 BHK flats of about 780 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.