Skip to main content
← Back

Destination EL Progreso B Building, Borhadewadi

Finishing stage

Final finishes 95% · completion not yet filed on MahaRERA

by EL Progreso Landmarks. Borhadewadi, Pune 412105. View on Google Maps

Launched
3 years 10 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stage
Units booked
126 of 17074% booked

Project facts

2 BHK74
3 BHK82
Other units (shops, offices or not given by type)14
Total units170
Buildings1
Land1 acre
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 128 → 126 · structure 38% → 100% · final finishes 0% → 95%

Share on WhatsApp

Compared with 6 similar projects in PIN 412105

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 10 mths3 yrs 10 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)December 2026December 2026
Concrete structure (RCC) complete100%100%
Share of units booked74%74%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 8 months of the promised 3 years 10 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 38%Dec 2024: Concrete structure (RCC) 38%Jun 2025: Concrete structure (RCC) 38%Dec 2025: Concrete structure (RCC) 38%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%126
100%38%0%128
100%38%0%11
0%0%0%11

"—" means MahaRERA shows no figure for that update.

About this project

Destination EL Progreso B Building (MahaRERA P52100049452) is a residential project by EL Progreso Landmarks in Borhadewadi, Pune 412105. It was launched in February 2023. It has 170 units in 1 building: 156 homes (2 & 3 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

126 of its 170 units are booked (74%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 38% to 100%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100049452.Check it on MahaRERA (P52100049452)All projects in Charholi, Moshi