by Turquoise Housing LLP. Somatane, Pune 410506. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Mar 2026 – Dec 2028varies by phase1 of 3 phases have an extended possession date. Reading a project's possession date
Concrete structure (RCC)
37%Mid-construction0 of 3 phases with structure completeWeighted across 3 phases
Units booked
56 units booked out of total 121 units

Project facts

Total units121
Buildings6
Land15.9 acres
Phases3
MahaRERA complaints (filed by or against the builder)0

Since Dec 2025: booked 41 → 51

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Supreme Villagio II
Mid-construction Lapsed
P52100049506095%94%
Supreme Villagio III
Mid-construction
P52100055048042%52%
Supreme Villagio IV
Mid-construction
PR126303250213501%14%
Show updates by phase

Supreme Villagio II (P52100049506)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%95%95%17
95%95%52%15
96%96%15%5
95%88%11%5
32%28%5%4

"—" means MahaRERA shows no figure for that update.

Supreme Villagio III (P52100055048)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
96%42%9%34
70%5%1%26
0%0%0%11
0%0%0%9

"—" means MahaRERA shows no figure for that update.

Supreme Villagio IV (PR1263032502135)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
52%1%0%5

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Supreme Villagio is a project by Turquoise Housing LLP in Somatane, Pune 410506, registered with MahaRERA as 3 phases (P52100049506, P52100055048, PR1263032502135). The first phase was launched in February 2023. Together the phases have 121 units in 6 buildings. On MahaRERA, 2 are active and 1 is lapsed.

The phases' registered possession dates run from March 2026 to December 2028; 1 of 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 37% complete and final finishes 19% complete. 0 of the 3 phases have their structure complete.

56 units booked out of total 121 units (46%).

Source: MahaRERA registrations P52100049506, P52100055048 and PR1263032502135.Open MahaRERA and search P52100049506All projects in Somatane