Lodha Panache, Hinjewadi

by Lodha Developers Limited. Hinjewadi, Pune 411057. View on Google Maps

Launched
First of 6 phases
Possession dates (MahaRERA)
Jun 2027 – Jun 2031varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
67%Mid-construction2 of 6 phases with structure completeWeighted across 6 phases
Units booked
1,022 of 1,26081% booked · 2 phases not reported
Price per sq ft
₹12,9002026 salesup 4% on 2025See what buyers paid

Project facts

1 BHK30
2 BHK763
3 BHK912
4 BHK61
5+ BHK8
Total units1,783
Buildings8
Land2.8 acres
Phases6
MahaRERA complaints (filed by or against the builder)3

Since Dec 2025: booked 938 → 1,022

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 860 sq ft₹1.06 – 1.13 crore2026 sales
3 BHKabout 1,130 sq ft₹1.40 – 1.47 crore2026 sales
4 BHKabout 1,740 sq ft₹2.14 – 2.29 crore2025 sales

Price per sq ft, year by year

2023₹10,200 per sq ft
2024up 14% on 2023₹11,600 per sq ft
2025up 7% on 2024₹12,400 per sq ft
2026up 4% on 2025₹12,900 per sq ft

Registered sales across all 6 phases.

Compared with the typical Hinjewadi rate in 2026: about 5% higher

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 6 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Hinjewadi Project
Nearing possession
P52100050124430100%87%
Hinjewadi Project-Tower 1
Mid-construction
P5210005125721585%87%
Hinjewadi Project-Tower 4 and 5
Nearing possession
P52100051280400100%74%
Hinjewadi Project-Tower 6
Mid-construction
P5210007776121585%77%
Hinjewadi Project-Tower A
Early stage
PR12600025007412550%Not reported
Hinjewadi Project-Tower B
Early stage
PR12600025007422590%Not reported
Show updates by phase

Hinjewadi Project (P52100050124)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%20%375
100%100%0%374
100%22%0%341
100%13%0%323
54%0%0%285

"—" means MahaRERA shows no figure for that update.

Hinjewadi Project-Tower 1 (P52100051257)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%186
100%53%0%185
100%13%0%161
100%6%0%149
100%0%0%108

"—" means MahaRERA shows no figure for that update.

Hinjewadi Project-Tower 4 and 5 (P52100051280)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%13%296
100%95%0%285
50%0%0%174
50%0%0%129
0%0%0%100

"—" means MahaRERA shows no figure for that update.

Hinjewadi Project-Tower 6 (P52100077761)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%165
100%50%0%94
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Hinjewadi Project-Tower A (PR1260002500741)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
20%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Hinjewadi Project-Tower B (PR1260002500742)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Lodha Panache is a project by Lodha Developers Limited in Hinjewadi, Pune 411057, registered with MahaRERA as 6 phases (P52100050124, P52100051257, P52100051280, P52100077761, PR1260002500741, PR1260002500742). The first phase was launched in March 2023. Together the phases have 1,783 units in 8 buildings, with 1, 2, 3, 4 & 5+ BHK homes as registered with MahaRERA. All 6 phases are active on MahaRERA.

The phases' registered possession dates run from June 2027 to June 2031; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 67% complete and final finishes 8% complete. 2 of the 6 phases have their structure complete.

1,022 of the 1,260 units reported for sale are booked (81%); 2 phases have not reported bookings. In 2026 registered sales, 80% of flats here sold at ₹12,900 per sq ft or less (up 4% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 5% higher than the typical Hinjewadi rate in 2026. Most buyers paid ₹1.06–1.13 crore for 2 BHK flats of about 860 sq ft (2026 sales); ₹1.40–1.47 crore for 3 BHK flats of about 1,130 sq ft (2026 sales); ₹2.14–2.29 crore for 4 BHK flats of about 1,740 sq ft (2025 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Lodha's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA56
Completed without extending the possession date15
Completed after an extension0
Lapsed0
Under construction41
Possession date extended on the builder's application5
Typical time from launch to 100% structure3 years 7 months
MahaRERA complaints (filed by or against the builder), all Lodha projects36 (17 of 56 projects)

See all Lodha projects →

Source: MahaRERA registrations P52100050124, P52100051257, P52100051280, P52100077761, PR1260002500741 and PR1260002500742.Open MahaRERA and search P52100050124All projects in Wakad, Hinjewadi, Marunji