Skip to main content
← Back

Capetown Heights, Charholi

by Anand Jadhav. Charholi, Pune 412105. View on Google Maps

Launched
7 years 3 months promised
Possession date (MahaRERA)
3 years 9 months awayPossession date unchanged since launch
Concrete structure (RCC)
8%Mid-constructionAverage across 4 buildings
Units booked
5 of 3714% booked

Project facts

1 BHK24
2 BHK13
Total units37
Buildings4
Land0.6 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Compared with 6 similar projects in PIN 412105

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)7 yrs 3 mths3 yrs 6 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)July 2030June 2027
Concrete structure (RCC) complete8%100%
Share of units booked14%46%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 6 months of the promised 7 years 3 months have passed
Concrete structure (RCC) 8% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 0%Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 25%Jul 2026: Excavation 25%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 8%Jul 2026: Concrete structure (RCC) 8%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 25%Concrete structure (RCC) 8%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
25%8%0%5
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Capetown Heights (MahaRERA P52100050285) is a residential project by Anand Jadhav in Charholi, Pune 412105. It was launched in April 2023. It has 37 units in 4 buildings, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is July 2030, unchanged since launch. Construction, averaged across its 4 buildings: excavation 25% complete, structure (RCC) 8% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

5 of its 37 units are booked (14%).

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050285.Check it on MahaRERA (P52100050285)All projects in Charholi, Moshi