Olive Homes -1, Charholi
Finishing stageLapsed
Final finishes 100% · completion not yet filed on MahaRERA
by Aakar Realties. Charholi, Pune 412105. View on Google Maps
- Launched
- 3 years 2 months promised
- Possession date (MahaRERA)
- 4 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- 78 of 9681% booked
Project facts
| 1 BHK | 78 |
|---|---|
| Other units (shops, offices or not given by type) | 18 |
| Total units | 96 |
| Buildings | 2 |
| Land | 0.4 acres |
| Landowner share | 16 |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: final finishes 95% → 100%
Compared with 6 similar projects in PIN 412105
Projects with 30–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 2 mths | 3 yrs 9 mths |
| Possession date extended | No | 1 of 6 |
| Possession date passed | Yes, due June 2026 | 1 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 100% | 74% |
| Share of units booked | 81% | 38% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Nakshatra i Land Phase 6 | April 2023 | December 2026 | 0% | All 95 units booked |
| Solitaire Empire | April 2023 | December 2026 | 100% | 79 of 98 booked (81%) |
| Dreams Carnival Platinum | April 2023 | December 2027 | 69% | 25 of 79 booked (32%) |
| Capetown Heights | April 2023 | July 2030 | 8% | 5 of 37 booked (14%) |
| Siddhivinayak Park Part 1 | June 2023 | December 2026 | 80% | 39 of 91 booked (43%) |
| Gandharv Mithila Building A Wing D | February 2023 | December 2026 | 100% | 1 of 47 booked (2%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 78 | |
| 100% | 100% | 95% | 78 | |
| 100% | 80% | 10% | 33 | |
| 100% | 35% | 0% | 20 | |
| 100% | 0% | 0% | 17 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Olive Homes -1 (MahaRERA P52100050733) is a residential project by Aakar Realties in Charholi, Pune 412105. It was launched in April 2023. It has 96 units in 2 buildings: 78 homes (1 BHK) and 18 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026. That date has passed and no extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
78 of its 96 units are booked (81%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.