Skip to main content
← Back

VJ IndiLife Wakad

Finishing stage

Final finishes 90% · completion not yet filed on MahaRERA

by Vilas Javdekar Lifestyle Developers Pvt. Ltd.. Wakad, Pune 411057. View on Google Maps

Launched
4 years 2 months promised
Possession date (MahaRERA)
8 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stage
Units booked
470 of 47699% booked

Project facts

1 BHK11
Other units (shops, offices or not given by type)465
Total units476
Buildings1
Land0.5 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 468 → 470 · final finishes 20% → 90% · complaints 0 → 1

Share on WhatsApp

Compared with 5 similar projects in PIN 411057

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 2 mths2 yrs 7 mths
Possession date extendedNo3 of 5
Possession date (MahaRERA)June 2027December 2026
Concrete structure (RCC) complete100%100%
Share of units booked99%56%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 6 months of the promised 4 years 2 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 30%Dec 2024: Concrete structure (RCC) 75%Jun 2025: Concrete structure (RCC) 75%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 20%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%470
100%100%20%468
100%75%0%459
100%30%0%458
100%0%0%448

"—" means MahaRERA shows no figure for that update.

About this project

VJ IndiLife Wakad (MahaRERA P52100050594) is a residential project by Vilas Javdekar Lifestyle Developers Pvt. Ltd. in Wakad, Pune 411057. It was launched in April 2023. It has 476 units in 1 building: 11 homes (1 BHK) and 465 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

470 of its 476 units are booked (99%). Since the December 2025 update, 2 more units have been booked.

Vilas Javdekar's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA45
Completed without extending the possession date25
Completed after an extension, or lapsed1
Under construction19
Possession date extended by the builder1
Typical time from launch to 100% structure2 years 10 months
Complaints on MahaRERA, all Vilas Javdekar projects27 (19 of 45 projects)

See all Vilas Javdekar projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050594.Check it on MahaRERA (P52100050594)All projects in Wakad, Hinjewadi, Marunji