Skip to main content
← Back

Eco City, Varale

Finishing stage

Final finishes 97% · completion not yet filed on MahaRERA

by Namrata Promoters and Builders. Varale, Pune 410507. View on Google Maps

Launched
2 years 9 months originally promised
Possession date (MahaRERA)
2 months agoExtended by 7 months (originally January 2026). Why possession dates change
Concrete structure (RCC)
100%Finishing stage
Units booked
92 of 9597% booked

Project facts

1 BHK95
Total units95
Buildings1
Land0.8 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 89 → 92 · possession date January 2026 → August 2026

Share on WhatsApp

Compared with 4 similar projects in PIN 410507

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 410507
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 9 mths3 yrs 6 mths
Possession date extendedBy 7 months1 of 4
Possession date (MahaRERA)August 2026April 2027
Concrete structure (RCC) complete100%100%
Share of units booked97%64%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 2 years 9 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 33%Jun 2024: Excavation 33%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 33%Jun 2024: Concrete structure (RCC) 33%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 9%Jun 2024: Final finishes 12%Dec 2024: Final finishes 71%Jun 2025: Final finishes 71%Dec 2025: Final finishes 97%Jul 2026: Final finishes 97%Excavation 100%Concrete structure (RCC) 100%Final finishes 97%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%97%92
100%100%97%89
100%100%71%42
33%33%12%—
33%33%9%—

"—" means MahaRERA shows no figure for that update.

About this project

Eco City (MahaRERA P52100050644) is a residential project by Namrata Promoters and Builders in Varale, Pune 410507. It was launched in April 2023. It has 95 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is August 2026, extended by 7 months from the original January 2026. Construction: excavation complete, structure (RCC) complete, final finishes 97% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

92 of its 95 units are booked (97%). Since the December 2025 update, 3 more units have been booked and the possession date has moved from January 2026 to August 2026.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050644.Check it on MahaRERA (P52100050644)All projects in Talegaon Dabhade, Darumbare