Ekdant, Kothrud
Finishing stage
Final finishes 90% · completion not yet filed on MahaRERA
by Swojas Icon Associates LLP. Kothrud, Pune 411038. View on Google Maps
- Launched
- 3 years 7 months promised
- Possession date (MahaRERA)
- 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Finishing stage
- Units booked
- 14 of 1593% booked
Project facts
| 2 BHK | 15 |
|---|---|
| Total units | 15 |
| Buildings | 1 |
| Land | 0.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Compared with 6 similar projects in PIN 411038
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 7 mths | 2 yrs 11 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | December 2026 | March 2027 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 93% | 28% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sarthak Aaradhana | May 2023 | June 2026 | 100% | All 28 units booked |
| Yoganand Park 2 | June 2023 | December 2025 | 100% | 2 of 12 booked (17%) |
| Self Redevelopment of Rajneel CHS | June 2023 | March 2027 | 100% | 5 of 19 booked (26%) |
| Aditi | April 2023 | March 2027 | 0% | 8 of 27 booked (30%) |
| Suparn | March 2023 | December 2025 | 100% | 5 of 26 booked (19%) |
| Suyog Laukik Apartment | July 2023 | December 2027 | 100% | 5 of 9 booked (56%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 95% | 100% | 90% | 14 | |
| 95% | 90% | 0% | 8 | |
| 95% | 90% | 0% | 5 | |
| 90% | 20% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Ekdant (MahaRERA P52100051099) is a residential project by Swojas Icon Associates LLP in Kothrud, Pune 411038. It was launched in May 2023. It has 15 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation 95% complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
14 of its 15 units are booked (93%).
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.