Skip to main content
← Back

Self Redevelopment of Rajneel CHS, Kothrud

Finishing stage

Final finishes 90% · completion not yet filed on MahaRERA

by Rajneel CHS Ltd. Kothrud, Pune 411038. View on Google Maps

Launched
2 years 9 months originally promised
Possession date (MahaRERA)
5 months awayExtended by 1 year (originally March 2026). Why possession dates change
Concrete structure (RCC)
100%Finishing stage
Units booked
5 of 1926% booked

Project facts

2 BHK13
3 BHK6
Total units19
Buildings1
Land0.1 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 2 → 5 · final finishes 0% → 90% · possession date March 2026 → March 2027

Share on WhatsApp

Compared with 6 similar projects in PIN 411038

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411038
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 9 mths3 yrs 3 mths
Possession date extendedBy 1 year1 of 6
Possession date (MahaRERA)March 2027January 2027
Concrete structure (RCC) complete100%100%
Share of units booked26%56%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 2 years 9 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 30%Dec 2024: Concrete structure (RCC) 90%Jun 2025: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%5
100%100%0%2
100%90%0%2
100%30%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Self Redevelopment of Rajneel CHS (MahaRERA P52100051229) is a residential project by Rajneel CHS Ltd in Kothrud, Pune 411038. It was launched in June 2023. It has 19 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

5 of its 19 units are booked (26%). Since the December 2025 update, 3 more units have been booked and the possession date has moved from March 2026 to March 2027.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100051229.Check it on MahaRERA (P52100051229)All projects in Kothrud